Title Page
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site Specific information for Christmas Shutdown
-
When will site close
-
When will site open
-
Person responsible for the site over holiday shutdown Name
-
Contact Number
Security measures in place for site fencing
-
Is security fencing braced so it cannot be pushed or blown over
-
Are all gaps under and around fencing and gates blocked so they cannot be crawled under or around <br>
-
Are access points locked or secured by mechanical means
Plant & Machinery security
-
Can plant and machinery be remove from site
-
Plant and machinery not removed from site MUST be secured and/or at least disabled
Chemical and potentially harmful substances storage
-
Have all chemicals and potentially harmful substances been removed from site
Electrical safety
-
Turn off main switch and lock or secure the main switchboard to prevent access
Construction area security
-
Brace and secure partially constructed building elements .... Secure against strong winds and bad weather
-
Secure any loose materials that could have the potential to turn into missiles
-
Back fill excavations , if required to remain open they should be covered or secured
-
Ensure all wast materials are removed from site
Sign off
-
Contractors Representative
-
Gippsland Water Responsible Officer
-
Auditor