Information
-
Project No.
-
Project
-
Area
-
Lot Number
-
Lot Description
-
Conducted on
-
Prepared by
GENERAL INSPECTION
-
Does the Project Specification call for specific test results to be provided? If yes please attach all test results / reports
-
Has the test equipment been calibrated?
-
Is the MEN link in position and connected correctly?
-
Have all labels for earth locations been shown in corresponding switchboard s?
-
Have labels been attached to earth stakes?
-
Has fault protection on MCCB's been set?
-
Gas cascading and discrimination of MCCB's been calculated?
POLARITY CHECK
-
Has the polarity checking been completed?
-
Were the polarity check results satisfactory?
-
Has the three phase rotation been checked on three phase circuits?
INSULATION RESISTANCE REST
-
Has the insulation resistance to all mains / submains / switchboards and equipment been tested?
EARTH CONTINUITY AND RESISTANCE
-
Has the earth resistance of the main earthing conductor been check? (Record result below)
-
Result in ohms
-
Has the earth continuity to each and every light point, power outlet or electrical appliance been confirmed?
RCD AND EFLI TESTS
-
Have RCD tests and earth fault loop impedance (EFLI) tests been carried out on power outlets, light points and equipment?
-
Is the EFLI results satisfactory in accordance with AS/NZS 3000:20070 Table 8.1?
-
Have all RCD units been functionally tested?
-
Operator name
-
Supervisors name