Information
-
HK Project Number
-
Project Name
-
Location
-
Conducted on
-
Prepared by
-
Personnel
-
LEGEND:
Compliant= 5. Opportunity for improvement= 3 Minor Non compliant= 2. Non compliant= 0 N/A= (No score)
Non compliance requires an action comment and an RFA HK.FM-33 to be raised
Minor non compliance requires an Action comment for follow up
Start up Checklist
-
1.1 Has the Project Initial Quality Review Checklist HK.FM-77 been implemented for this project
-
1.2 Has the Project Initial Environmental Review checklist HK.FM-88 been implemented for this project
-
1.3 Is the Master Document Register HK.FM-40 on site and up to date
-
1.4 Has the Project Specific Major Risk Register HK.FM-95 been implemented for this project
-
1.5 Are all appropriate forms, registers, HK policy statements, basic rules, safety alerts and posters on display
Site Organisation
-
2 .01 Is the WHS Management Plan HK.FM-66 being maintained and up to date
-
2.02 Is the Environmental Management Plan HK.FM-104 being maintained and up to date
-
2.03 Is the Inspection Test Plan (ITP) HK.FM-63 being maintained
-
2.04 Are completed documents filed in their correct folders. Namely separate folders for Site Inductions, SWMS. While the WHS Management Plan is to contain JSA reviews, permits, toolbox talks, Plant & Machinery checklist
-
2.05 Have all workers signed in via a site sign in book or using a site specific sign in procedure
-
2.06 Is a First Aid Register HK.FM-03 available for use together with an appropriate 1st Aid Kit
-
2.07 Are 1st Aid personnel nominated and displayed.
-
2.08 Is there an Emergency Contact Register HK.FM-27 on display
-
2.09 Is there an up to date Evacuation Plan on site
-
2.10 Is a Hazardous Chemical Register HK.FM-90 being used and maintained.<br>
-
2.11 Are permits for Hot Works, Working at Heights and Confined Space being used and maintained
-
2.12 Is the Plant and Machinery Inspection Checklist HK.FM-94 being used and maintained
-
2.13 Is there a H&K SDS register on site and accessible for all workers.
-
2.14 Are Subcontractors presenting with SDS sheets for their own materials coming on site
-
2.15 Have Site Inductions HK.FM-99 been fully completed <br>
-
2.16 Have Subcontractor SWMS been presented and signed off by all relevant workers
-
2.17 Are Subcontractor JSA Review checklists HK.FM-96 being used on all SWMS
-
2.18 Are toolbox meetings being conducted and recorded on HK.FM-14
-
2.19 If applicable to this Project, do all Subcontractors have Police or DCSI clearances
-
2.20 Is an evacuation drill planned and on what date<br>
-
2.21 Has the drill been carried out on the scheduled date and recorded on HK.FM-24
Site Observations
-
3.1 Are workers performing their tasks according to their SWMS
-
3.2 Has all electrical equipment been tested, tagged and up to date.
-
3.3 Are all electrical leads being managed on site in a safe manner.
-
3.4 Does the workplace area have adequate lighting.
-
3.5 Are fire extinguishers located within ready access to an exit.
-
3.6 Do the extinguishers have a current test tag<br>
-
3.7 Are gas bottles secured in a trolley or secured to a wall
-
3.8 Is the site or work area free from rubbish and obstructions.
-
3.9 Is the site waste being sorted for recycling
-
3.10 Have hazardous objects, openings or areas been protected or isolated.
-
3.11 Are materials being stored in a safe and orderly manner
-
3.12 Are hazardous chemicals labelled and stored correctly
-
3.13 Are site amenities being kept clean and well maintained.
Evaluation
-
4.1 Are Site Safety Audits HK.FM-97 being undertaken at the frequency declared in the WHS Management Plan HK.FM-66
-
4.2 Are Environmental Audits HK.FM-89 being undertaken at the frequency declared in the Environmental Management Plan HK.FM 104
-
4.3 Have all outstanding issues from the previous audits been dealt with
Auditors Comments:
-
5.1 Detail any issues from this audit that could be improved
-
5.2 Detail any issues from this audit that requires an RFA to be raised
-
Close Out Signature .