Information

  • HK Project Number

  • Project Name

  • Location
  • Conducted on

  • Prepared by

  • Personnel

Start up Checklist

  • If there is a no response to any of the questions below, please complete the action field so corrective action can be taken

  • 1.0 Has the Project Initial Quality Review checklist HK.FM-77 been completed

  • 1.1 Has the Project Initial Environmental Review checklist HK.FM-88 been completed

  • 1.2 Has an Inspection & Test Plan (ITP) HK.FM 63 been created and is being maintained

  • 1.3 Is the Master Document Register HK.FM-40 on site and up to date

  • 1.4 Has the Project Specific Major Risk Register HK.FM-95 been issued, monitored and being maintained

  • Other

Site Organisation

  • 2.0 Is the WHS Management Plan HK.FM-66 on site and upto date.

  • 2.1 Is the Environmental Management Plan HK.FM-104 on site and up to date

  • 2.2 Are all appropriate forms, registers, policy statements, safety alerts and posters on display

  • 2.3 Are Confined Space, Hot Work, Working at Height permits being used and maintained on file

  • 2.4 Is a First Aid Register HK.FM-03 on site and being maintained along with 1st Aid Kit

  • 2.5 Is the Emergency Contact Register HK.FM-27 on site and relevant to current site location<br>

  • 2.6 Is the Evacuation Plan current and located at different areas of the site when deemed necessary

  • 2.7 Is the Plant and Machinery Inspection Checklist HK.FM-94 being used and maintained on all machinery

  • 2.8 Is the Hazardous Chemical Register HK.FM-90 being used and maintained.<br>

  • 2.9 Is there an H&K SDS register on site and accessible for all workers.

  • 2.10 Are all Subcontractors presenting the SDS sheets for their own materials coming on site

  • 2.11 Have all workers signed on today

  • 2.12 Are all current Subcontractors listed on the WHS Management Plan

  • 2.13 Are SWMS being signed off by all relevant workers.

  • 2.14 Are Subcontractor JSA Review Checklists HK-FM 96 being used to assess all SWMS

  • 2.15 Are all relevant SOPs available on site for machinery, plant and equipment being used.<br>Also applies to Subcontractors <br>

  • 2.16 Are toolbox meetings being conducted and recorded on HK.FM-14

  • 2.17 Are Site Safety Internal Audits HK.FM-97 being undertaken at the frequency declared in the WHS Management Plan HK.FM-66

  • 2.18 Are Environmental Monitoring Audits HK.FM-89 being undertaken at the frequency declared in the Environmental Management Plan HK.FM-104

  • 2.19 Where required, do all Subcontractors have Police or DSCI clearances

  • Other

Site Observations

  • 3.0 Have adequate control measures been taken to make the site safe from nearby services such as gas, electricity, water and sewerage telecommunications

  • 3.1 Have measures been taken to allow for exposure to noise, heat, cold, vibration, radiation, static electricity, or contaminated atmosphere

  • 3.2 Is there adequate separation from the client user groups and/or members of the public<br>Ie. separating work site from non-workers

  • 3.3 Is the correct PPE being worn or used by workers

  • 3.4 Are the individual requirements of the SOPs and SWMS being followed by all workers.

  • 3.5 Does the workplace area have adequate lighting.

  • 3.6 Are walking areas inside and out free of hazards

  • 3.7 Are there protective devices, isolation measures or barriers located at hazardous objects

  • 3.8 Have control measures been taken to prevent moving plant from striking a worker

Electrical

  • 4.0 Are all power supply outlets in good condition and safe to use

  • 4.1 Are all electrical leads/extension cords in good condition and currently tested and tagged

  • 4.2 Are power boards market to indicate source of supply and feed-in wiring marked with “caution temporary construction wiring” yellow identification

  • 4.3 Has live permanent wiring passing through the building site been marked with live red wiring identification tape

  • 4.4 Are all electrical tools in good condition, currently tagged and equipment protected by an RCD box or switch

  • 4.5 Are cable management systems in place, leads kept off the floor and managed safely

  • Other

Storage

  • 5.0 Are all hazardous substances clearly labelled and stored in a neat and orderly manner

  • 5.1 is there an SDS for such substances

  • 5.2 Are gas bottles securely fastened to a trolley and removed from site each night or stored safely and securely in a well ventilated area

  • 5.3 Are materials being stored in a safe orderly manner.

  • Other

Hygiene

  • 6.0 Is signage displayed in kitchen area detailing household rules re tidiness and cleanliness

  • 6.1 Have adequate site amenities been provided which are clean and tidy, with cleaning products available for regular maintenance

  • 6.2 Are garbage bag lined bins available for all food scraps and kitchen waste

  • 6.3 Is clean drinking water available to all contractors

  • 6.4 Is there adequate, clean, hand washing and toilet facilities, with provisions for regular cleaning

  • 6.5 Is there a bin available for waste paper towelling disposal

  • 6.6 Are site amenities being kept clean and well maintained.

Evacuation

  • 7.0 Is the Fire Policy and a Evacuation Plan clearly visible and gives details of <br>-position of fire extinguishers<br>-escape routes and exits<br>-the assembly point(s)

  • 7.1 Has an evacuation drill been conducted within the last 12 months with all workers participating. If not, when is one planned <br>

  • 7.2 Do exit signs clearly show the way out of the building(s)

  • 7.3 Are exit doors clearly identified, free of obstructions and unlocked during working hours

  • 7.4 Are ignition sources kept to a minimum and separated from combustible material

  • 7.5 Are fire extinguishers located nearby to an exit, suitable for probable fire type, and within 6 months of last test tag

  • Other

Falling Objects

  • 8.0 Are there adequate provisions for lowering/ raising materials, plant and debris

  • 8.1 Are fall arrest devices for heights > 2m being used where there is no protective fall barrier

  • 8.2 Is there a contingency rescue plan in place from a fall arrest device

  • 8.3 Have control measures been taken to prevent objects falling and striking a worker

  • Other

Ladders and Scaffold

  • 9.0 Are A-frame ladders fully open, locked in position and in good condition

  • 9.1 Have you considered using a better alternative to A-frame ladders such as platform ladder, scaffold,

  • 9.2 Is the single ladder securely fixed and extends 1 metre above the top platform

  • 9.3 Are the ladders and scaffolds positioned away from the doorways

  • 9.5 Are the ladders and scaffold at least 4.6m from bare electrical conductors

  • 9.6 Are non-conductive ladders being used where an electrical hazard exists

  • 9.7 Has the portable scaffolding been erected in the correct manner <br>Ie adequate safety rails, kick boards, internal ladders, correct diagonal bracing, outriggers if required.

  • Other

Evaluation

  • 10.0 Have any previous been action items been rectified and closed out.

  • 10.1 Is the site free of any current non conformance issues.<br>Please summarise here the actions required

Auditors Comments:

  • Close Out Signature .

  • Form No HK.FM-97 (revision 1)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.