Title Page

  • Site

  • Conducted on

  • Prepared by

  • Client

  • Job Number

  • Document No.

  • Footing purpose

Checks, tests and verification

  • Set out of site correct as per drawing?

  • If scope changed, has PM or client rep approved the changes?

  • If location/size of footing changes, mark up as builts

  • Depth of concrete

  • Excavation dimensions (width and depth) correct and free from organic matter, loose material and voids?

  • Steel reinforcing type correct, adequetly lapped, tied, supported and concrete cover achieved?

  • Depth of concrete maintained at piping or conduit penetrations

  • Footing inspected prior to concrete pour. Correct conduits and bends placed in correct location as per drawings

  • Photos of footing prior to concrete pour

  • Conduits emerging at suitable position

  • Proposed finished floor level appears to be correct at this stage of construction

  • Comments/Remarks

  • Photos after concrete pour

  • Sign off

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.