Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Photo of Construction Permit
Permit / Notifications Requirements
-
Is a Notification required?
-
Did the Contractor notified the DoL regarding the construction work?<br>CR 4(1)
-
Was the notification send to DoL 7 days prior to the start of the construction work?<br>CR 4(1)
-
Is the Notification available on site?
-
Is a Permit from DoL required?
-
Has a permit been obtained for the construction work by the Client?<br>CR 3(1)
-
Did the Client appointed a Construction Health & Safety Agent?<br>CR 5(5)
-
Is the permit displayed on the entrance gate?<br>CR 3(4)
-
Is a copy of the permit in all the Principle Contractors Health & Safety Files<br>CR 3(6)
Legal Appointments: The following appointments might be required - verify against the actual work to be done on site
-
Construction Health & Safety Agent (if required)<br>CR 5(5)
-
Is the CHSA properly registered with the SACPCMP?<br>Verify the registration certificate
-
Any additional comments
-
Designer - Principle Contractor & Client appointments<br>CR 6
-
Principle Contractor<br>CR 5(1)(k)
-
Sub-Contractors<br>CR 7(1)(c)(v)
-
List the Sub-contractors at the time of the audit
-
Section 16.2 Appointees<br>S16.2
-
Competent person for Machinery<br>GMR 2(1)
-
Construction Manager<br>CR 8(1)
-
Assistant Construction Manager<br>CR 8(2)
-
Construction Supervisors<br>CR 8(7)
-
Assistant Construction Supervisors<br>CR 8(8)
-
Construction Health & Safety Officer<br>CR 8(5)
-
Is the CHSO registered with the SACPCMP
-
Employee Health & Safety Representatives<br>Sec 17
-
Employer Health & Safety Representatives<br>Sec 17
-
First Aiders<br>GSR 3
-
Incident Investigator<br>GAR 9
-
Person responsible for conducting Risk Assessments<br>CR 9(1)
-
Fall Protection Plan - Responsible person for developing & maintaining<br>CR 10(1)
-
Temporary Works Designer<br>CR 12(1)
-
Temporary Works Supervisor<br>CR 12(2)
-
Excavation Supervisor<br>CR 13(1)(a)
-
Demolition Supervisor<br>CR 14(1)
-
Scaffold Erector<br>CR 16(1)
-
Suspended Platform Supervisor<br>CR 17(1)
-
Rope Access Supervisor<br>CR 18(1)(a)
-
Material Hoist Supervisor<br>CR 19(8)
-
Bulk Mixing Plant Supervisor<br>CR 20(1)
-
Explosive Actuated Fastening Devices Issuer & Inspector<br>CR 21(2)(b)
-
Tower Crane Erection Supervisor<br>CR 22(a)
-
Lifting Machine Operator<br>GMP
-
Operators of Construction Vehicles & Mobile Plant<br>CR 23(d)(ii)
-
Responsible Person for Temporary Electrical Installation & related equipment<br>CR 24(d)
-
Stacking & Storage Supervisor<br>CR 28(a)
-
Competent person responsible for fire fighting equipment and emergency evacuation procedures?<br>CR 29(h)
-
Fire & Emergency Co-ordinator<br>GMP
-
Fire Marshall<br>GMP
-
Ladder Inspector<br>GMP
-
Hand Tools Inspector<br>GMP
-
Hazardous Chemical Substance Co-ordinator<br>GMP
Functioning of Health & Safety Representatives
-
Is this Category applicable?
-
Can Contractor proof that the H&S Reps were nominated by employees?<br>Sec 17 & 18
-
Are regular inspections done and are those records available on site?<br>Sec 18
-
Are H&S Reps involved during incident investigations?<br>GAR 9
-
Is there a H&S Representative Committee established and are minutes of the meetings held available on site?<br>GAR 19
Reporting & Investigation of Incidents
-
Are comprehensive incident reports for all fatalities & permanent disability cases sent to the DoL?<br>CR 5(3)
-
Are all Incidents as per Section 24, 25 & GAR 8 reported to the DoL?<br>CR 5(3)
-
Are all incidents requiring medical treatment recorded on Annexure 1 forms and is it properly investigated?<br>GAR 9
Health & Safety Plan & File
-
Did the Principle Contractor submit a comprehensive and detailed H&S plan to the Client & was the plan approved by the Client?<br>CR 7(1)(a) & CR 5(1)(l)
-
Is the H&S plan site & project specific?<br>CR 7(1)(a)
-
Does the Health & Safety Plan complies and addresses all issues as per legal requirements? - Risk Assessments<br>CR 9(1)
-
Are Ergonomic risks addressed in the Health & Safety Plan?<br>CR 9(2)
-
Are employees on site trained on the content of the Health & Safety Plan?<br>CR 9(3)
-
Are the Health & Safety Plans for Principle & Sub Contractors reviewed after incidents and when changes are made in the design?<br>CR 9(7)
-
Are the Health & Safety files kept by the Principle & Sub Contractors on site and is it available for inspection?<br>CR 7(1)(b) & CR 7(2)(b) & CR 5(1)(m)
Fall Protection
-
Is this Category applicable?
-
Is the Fall Protection Plan drafted and contain all the information as per the legal requirement?<br>CR 10(2)
-
Are opening in floors or sides of floors from through or from which persons fall enclosed with handrails<br>CR 10(3)
-
Are the Fall Arrest / Prevention equipment sufficient for the purpose of use and securely attached to a safe point on the structure or plant?<br>CR 10 (4)(c)(i) & (ii)
-
Are Fall Arrest equipment only used in instances where Fall Protection equipment cannot be used?<br>CR 10(4)(d)
-
Are employees trained on the Fall Protection Plan and are the training records available on site?<br>CR 10(2)(c)
Duties of Principle Contractor to Sub-contractor
-
Is this Category applicable?
-
Are periodic site audits conducted of all work performed by Sub-Contractors - at least every 30 days?<br>CR 7 (1)(c)(vii) & CR 5 (1)(o)
-
The Principle Contractor have a list of all Sub-Contractors on site and contains information on accountability, agreements signed and type of work to be performed?<br>CR 7(1)(f)
-
Are contractors stopped when doing work in an unsafe manner or when it is not done in line with the Health & Safety Plans?<br>CR 7(1)(c)(viii)
-
Are all the Health & Safety files of Sub-Contractors approved & signed by the Principle Contractor?<br>CR 7(1)(c)(x)
-
Are Health & Safety Files available on site for all the Sub-Contractors?<br>CR 7(1)(d)
-
Are all the Sub-Contractors registered and in good standing with COIDA or other licensed compensation insurer as per COIDA - is the letters available on site?<br>CR 7(1)(c)(iv)
-
Have all Sub-Contractors been appointed in writing and appointment letters is available on site?<br>CR 7(1)(c)(v)
Medical Certificates of Fitness
-
Are all the employees of the Principle Contractor on site in possession of a valid medical certificate of fitness issued by an OHP?<br>CR 7(8)
-
Are all the medical certificates of fitness issued in the form of Annexure 3?<br>CR 7(8)
-
Does the medical certificate of fitness issued address all possible exposure and job specifications?<br>CR 7(8)
Induction Training ( Staff & Visitors)
-
Do all visitors to the site receive induction training and are those training records kept on site?<br>CR 7(6) & (7)
-
Did all employees employed on site received induction training and are those training records kept on site?<br>CR 7(5) & (7)
Roof Work
-
Is this Category Applicable?
-
Is roof work properly planned?<br>CR 10(5)(a)
-
Are weak areas and openings on the roof covered?<br>CR 10(5)(d)
-
Are roof ladders, duct boards or other safety devices or equipment available that is suitable to the weights of persons performing work?<br>CR 10(5)(e)
-
No roof work are allowed during bad weather?<br>CR 10(5)(c)
-
Where possible, are handrails, barriers & toe boards installed along the side of the roof?<br>CR 10(5)(f)
Temporary Works
-
Is this Category applicable?
-
Are all temporary works erected in accordance with the structural design drawings?<br>CR 12(3)(b)
-
Are all the design drawings & calculations for temporary works kept on site?<br>CR 12(3)(c) & CR 6(2)
-
Are all staff members required to perform work on a temporary works properly trained?<br>CR 12(3)(d)
-
Are all the equipment used in temporary works inspected before use?<br>CR 12(3)(e)
-
Are all temporary works inspected before, during & after placement of concrete and at least daily and a register is kept?<br>CR 12(3)(f)
-
Concrete is only casted after written permission has been granted by the Temporary Works Supervisor?<br>CR 12(3)(g)
-
Are safe means of access provided to all temporary works?<br>CR 12(3)(m)
Excavations
-
Is this Category applicable?
-
Are all excavations inspected daily, after blasting, after fall of ground, after damage to supports & after rain. Is a register kept of all inspections?<br>CR 13 (2)(h)
-
Are all excavations sufficiently safeguarded from collapse?<br>CR 13(2)(b)
-
Are excavation accessible to the public safeguarded by 1m high barrier or fence and when poor visibility is present with warning flashing lights?<br>CR 13 (i)(i & ii)
Demolition Work
-
Is this Category applicable?
-
Was a detailed structural engineering survey carried out prior to any demolition work?<br>CR 14(2)
-
Material are not disposed of from heights unless it is done using a chute and that the chute is constructed of sound material and strong enough to handle the load?<br>CR 14(5) & (6) & (7)
-
If asbestos is present, did the contractor submitted a workplan to DoL?<br>CR 14(9)
-
Are the asbestos work done by a DoL approved Asbestos Contractor?<br>CR 14(9)
-
Are monitoring been conducted by an DoL approved AIA during the asbestos demolition process?<br>CR 14(9) & AR 8
-
Has a method statement been drafted and implemented for tasks requiring the use of explosives?<br>CR 14(11)
Scaffolding
-
Is this Category applicable?
-
Are all scaffolding erected & use in compliance with provisions od SANS 10085?<br>SANS 10085 & CR 16
-
Are all scaffolding inspected after erection and before use, weekly, after damage, after rain and before demolition and is a register kept of these inspections?<br>SANS 10085 & CR 16
Suspended Platforms
-
Is this Category applicable?
-
Has a Certificate of System Design been issued by a Professional Engineer for the Suspended Platform in use? <br>CR 17(2)(b)
-
Is an Operational Compliance Plan drafted & implemented that address all the requirements as per CR 17(2)(c)?<br>CR 17(2)(c)
-
Were copies of the Certificate of System Design & Operational Design Drawings submitted to DoL prior to the use of the Suspended Platform? <br>CR 17(3)
-
Are all staff working inside the Suspended Platform wearing full body harnesses? <br>CR 17(6)(c)
-
Are hand & power tools used inside the Suspended Platform secured to prevent movement? CR 17(6)(d)
-
Are a notice indicating the maximum mass load, maximum number of persons & maximum load fitted inside the Suspended Platform? <br>CR 17(7)(c)
-
Is the Suspended Platform inspected and load tested at intervals as per the manufacturer's instruction? <br>CR 17(8)(d)
-
Are all ropes and hooks inspected after assembly & before use and at intervals not exceeding 3 months? <br>CR 17(9)
-
Are daily inspections carried out that cover all issues as per legal requirement? <br>CR 17(10)
-
Are inspections & test records available on site? <br>CR 17(11)
-
Are all the operators of Suspended Platforms trained in the safe use of equipment & body harnesses & emergency procedures? <br>CR 17(12)
-
Are outriggers only moved by competent persons and the installation inspected by a supervisor prior to use? <br>CR 17(13)
-
Are the Suspended Platforms properly secured while not in use as to prevent unauthorised use?<br> <br>CR17(14)
Rope Access Work
-
Is this Category applicable?
-
Are all the rope access staff members properly registered and licensed for the task to be performed?<br>CR 18(1)(c)
-
Are the rope access equipment used safe and in compliance with safety standards?<br>CR 18(2)(a)
-
Is a rescue plan drafted and implemented?<br>CR 18(3)
Material Hoists
-
Is this Category applicable?
-
Were all material hoists erected as per technical standard?<br>CR 19(1)
-
Are all the sides of the material hoist on ground & floor level enclosed up to at least 2.1 meter?<br>CR 19(2)(b)
-
Are gates which is at least 2.1 meter in height installed at all landings?<br>CR 19(2)(c)
-
Are items transported on the material hoists secured as prevent movement?<br>CR 19(4)
-
Are the maximum loading capacity displayed on the material hoist?<br>CR 19(5)
-
Are material hoists inspected daily and is a register kept of all inspections?<br>CR 19(8)
Explosive Actuated Fastening Devices (EAFD)
-
Is this Category applicable?
-
Are all the EAFD's in compliance and safe for use?<br>CR 21(1)
-
Are all EAFD's inspected daily and is a register kept of all the inspections?<br>CR 21(2)(b)
-
Are records kept of all EAFD's and cartridges issued?<br>CR 21(2)(g)
Lifting Machines & Cranes
-
Is this Category applicable?
-
Are all lifting tackle inspected at intervals not exceeding 3 months and registers kept for such inspections?<br>DMR 18
-
Are all lifting machines inspected by an LME & LMI at intervals not exceeding 6 months and registers kept for such inspections?<br>DMR 18
-
Are all lifting machines load tested by LME & LMI at intervals not exceeding 12 months and registers kept for such load testing?<br>DMR 18
-
Are the operators of lifting machines and cranes properly trained and are the training records available on site?<br>CR 22(e)
Construction Vehicles & Mobile Plant
-
Is this category applicable?
-
Are all operators trained and competent to operate the equipment? CR 23(1)(d)
-
Are all the vehicles and mobile plant fitted with signalling and reverse signalling devices? CR 23(1)(f) & (j)
-
Are all vehicles and mobile plant fitted with structures preventing items falling onto the operator? CR 23(1)(h)
-
Are all vehicles and mobile plant inspected daily and is a register of such inspections available on site? CR 23(1)(k)
-
Are vehicles and mobile plant used for the transportation of staff fitted with seats for each person being transported? CR 23(2)(i)
Electrical Equipment
-
Are Electrical Certificate of Compliance available for all temporary switchboards or electrical connections used?<br>EIR 7
-
Are all temporary electrical installations inspected weekly by a competent persons and is a register kept of such inspections?<br>CR 24(d)
-
Are all portable electrical equipment inspected daily and is a register kept of such inspections?<br>CR 24(e)
Use & Storage of Flammable Liquids
-
Is this Category applicable?
-
Are all flammable liquids properly & safely stored on site?<br>CR 25(a)
-
Are smoking prohibited near the flammable storage facility?<br>CR 25(b)
-
Are there sufficient fire fighting equipment installed in close vicinity of the flammable storage and are the symbolic signs in place?<br>CR 25(c)
-
Are no more of 1 days quantity of flammable liquids issued from the store?<br>CR 25(d)
-
Are all flammable liquid containers kept close when not in use?<br>CR 25(e)
-
When decanting, are all the metal containers bonded and earthed?<br>CR 25(f)
-
Are flammable containers stored separately from other flammable materials such as rags, paper etc...<br>CR 25(g)
Work Performed Close to Water
-
Is this Category applicable?
-
Are fall protection & fall arrest or life jackets made available to staff who perform work in close proximity to water?<br>CR 26
Housekeeping & General Safeguarding of Site
-
Are good housekeeping practices implemented and maintained on the site?<br>CR 27
-
Is the construction site properly fenced off with controlled entrance?<br>CR 27(f)
-
Are nets & catch platforms erected above areas where persons pass as to prevent items from falling onto them?<br>CR 27(g)
Stacking & Storage
-
Are good stacking & storage practices implemented and maintained on the site? (check for demarcation, cleanliness, inspections)<br>CR 28
-
Stacking heights do not exceed 3 times the smallest dimension of the underlying base?<br>GSR 8
Fire Precaution
-
Are sufficient quantities & correct type of fire fighting equipment available on site?<br>CR 29
-
Are all the fire fighting equipment inspected by a competent person and is a register kept of such inspections?<br>CR 29(h)
-
Are Fire Marshalls appointed and properly trained?<br>CR 29(I)
-
Is an evacuation plan drafted & implemented?<br>CR 29(l)
-
Is there a fire siren available on site?<br>CR 29(m)
Toilets & Change Room Facilities
-
Is this Category applicable?
-
Are there at least 1 shower available for every 15 staff members?<br>CR 30(1)(a)
-
Are there at least 1 toilet available for every 30 staff members?<br>CR 30(1)(b)
-
Are there change facilities for each sex?<br>CR 30(1)(c)
-
Are sheltered eating areas available to all staff?<br>CR 30(1)(d)