1. Risk Assessment & SSOW
-
Specific, Communicate to All, In date 12 months, All risks covered & Environmental risks controlled. (Total score 10)
2. LOLER & PUWER Documentation
-
Cranes, MEWPs, Towers, Tools etc (score 10)
3. PPE
-
Task specific, Hearing Protection & Safety Goggles, Correct Dust Masks (FFP3 etc) (score 10)
4. Housekeeping & Safe Access
-
Clean Walkways, Access Steps, No Trailing Leads & Tidy Materials (score 10)
5. Working at Heights
-
Safe Work on Towers, Ladders, Tied/Footed, Ladder Tags & Handrails (score 25)
6. Pre Op Inspections
-
Cranes, Saws, Hand-tools & MEWPs (score 20)
7. Supervision
-
SSSTS, SMSTS, Lift Supervisor (score 20)
8. Training & Competency
-
Toolbox talks, MEWPs, Copies of Training (score 20)
9. Lifting Operations
-
Lift Plan, Lift Zone Clear, Equipment Certified, Training Operators & Safe Lifting (score 25)
10. Temporary Works
-
Prop Procedure, Tags, TWC, TWS (score 25)
11. Environmental & COSHH & Stored Correctly
-
IBC Storage, Drip Trays, COSHH, Assessments & Substances labeled Correctly (score 10)
12. Health
-
Signs, Dust Management, Noise, Skin, Vibration (score 10)
13. Safety Devices
-
Safety devices in cranes must not be overridden. (Score 10)