Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Pre-Construction
General
-
1. Is the site construction facility, materials handling and parking areas located in approved clear areas?
-
2. Have all planning approvals and permits been obtained pertaining to environmental and heritage requirements for the project? (such as native vegetation offsets, wildlife permit, permit to disturb, CHMP)
-
3. Is there a requirement to implement any flora or fauna specific targeted survey, translocation plan or conservation management plan for the works? (I.e GGF, GSM, SLL, Spiny Rice-flower, etc)
-
4. Has a permit(s) from Council been obtained to remove/prune/lop any trees on site?
-
5. Has a Weed Management Plan been specified for the works?
-
6. Is a Tree Management Plan required for the works?
Pre-Commencement
Flora and Fauna
-
7. Does the contractor have a copy of the Environmental Management Plan on site?
-
8. Has the contractor undertaken environmental awareness training and/or site induction to toolbox flora and fauna issues?
-
9. Has the contractor outlined specific measures to protect any sensitive flora and fauna habitat and/or vegetation outside of the Works area during construction, and are these areas identified in the construction plans? ( I.e location of exclusion or temporary fencing, para webbing, star pickets)
Cultural Heritage
-
10. Does the contractor have a copy of the CHMP/Heritage Permit on site?
-
11. Have all contractors undertaken indigenous cultural awareness training?
-
12. Have all contractors involved in ground works signed in to the Cultural Heritage Register?
-
13. Has the contractor confined all works within the Activity Area specified in the CHMP/Heritage Permit?
-
14. Have exclusion zones protecting Aboriginal cultural heritage been identified as per the CHMP/Heritage Permit, and marked on construction plans?
Site EMP
-
15. Does the Site EMP stipulate all required legislative permits and approvals specific to the works? ( I.e EPBC Act, FFG Act, Wildlife Act, Fisheries Act, Water Act, Environment Act, EPA approval, Melbourne Water permit, Council planning permit, Native vegetation offsets, Wildlife permit, Permit to disturb, CHMP)
-
16. Does the Site EMP contain a Waste Hierarchy Management Plan which outlines management of all waste on the site?
-
17. Does the Site EMP specify effective measures for site restoration and clean up?
-
18. Does the Site EMP stipulate actions for weed management during construction?
-
19. Does the Site EMP specify actions for tree management?
-
20. Does the Site EMP specify measures to minimise construction impacts to sensitive areas? (such as waterways, native vegetation, nearby residents)
-
21. Does the Site EMP include a risk assessment methodology that risk ranks specific environmental and heritage related aspects in relation to the construction project?
-
22. Does the Site EMP specify protective measures to contain or minimise generation of dust and of our on site?
-
23. Does the Site EMP specify storage and spill management practices to be implemented to prevent and/or minimise environmental damage resulting from chemical or fuel leakage?
-
24. Does the Site EMP specify management practices to be implemented for wash-out of concrete of trucks?
-
25. Does the Site EMP stipulate maintenance of MSDS records for all fuel and chemicals used on site?
Post-Construction
-
26. Has the contract left silt fences in position to assist with re-instatement?
-
27. Has the contractor completed the site re-instatement to allow for seeding, replanting and landscaping?
-
28. Has the contractor adequately maintained all landscaped areas affected by construction works? Have landscaped and/or revegetated areas effectively re-established post construction?
-
29. Has the contractor completed all follow up weed management requirements post construction?
-
30. Has the topsoil been adequately leveled and graded out by the contractor to the satisfaction of the landowner?
-
31. Is there evidence of erosion as a result of completion of construction works?
-
32. Is the topsoil/finished surface free of debris and inorganic matter? (such as stones/rocks/glass etc)
-
33. Where groundwater has been discharged to land, has the area distributed effectively re-established post construction?
-
34. Is there evidence of any adverse impacts to trees as a result of construction?
-
35. Have all stockpiles, excavated materials and quarry products been removed by the contractor post construction?
-
36. Are drains in the vicinity of the worksite free of dirt, silt and debris?