Is there rebar on the deck impacting layout
-
Are you using the most up to date drawings
-
Are you using the correct blue banger size for the hanger rod size
-
Have you verified that all deck sleeves are the right size for the piping that penetrates through it
-
Are all deck sleeves set to 1/8-1/4 below finish floor
-
Are all deck sleeves secured properly fastened to the deck
-
Have you spot checked hard dimensions off of column lines for the deck cans
-
Have any sleeves or cans been damaged?
-
Are all drains secured and fasten to the deck
-
Are the drains set to the correct height
-
Are the drains installed the correct size
-
Is the drain the correct type of drain I.E.- floor drain, area drain, storm drain
-
If the drains call for a piece of pipe to be installed are bands torqued to spec
-
Is all exposed cast iron pipe in pour foam wrapped
-
Are threads for all adjustable drains wrapped and protected
-
Are all floor sinks set 1/4 above finish floor
-