Title Page
-
Report Type
- Electrical 1st Fix Handover Report
-
Contract
-
Location
-
Plot No.
-
Conducted on - Year.Month.Day
-
Prepared by
-
Installation Date
-
Comments
-
Location Photo
-
Installation by
-
Plots completed as per program and handed over ready for HES to start works.
-
Plot Inspected and was ready for 1st Fix
-
Comments
-
Installed to drawing numbers
-
List drawing numbers and revision number
-
Installation as per drawings
-
Comments
-
Kitchen Installation as per kitchen drawings
-
Comments
-
Dimensions and Heights correct
-
List Items and Location to Items it Applies to
-
Correct outlet boxes and caddy straps installed and all secure
-
List Items and Location to Items it Applies to
-
Cables mechanical protection in place
-
List Items and Location to Items it Applies to
-
LV Cables in position, labelled, neat, cable ties cut, cables secure.
-
List Items and Location to Items it Applies to
-
ELV Cables in position, labelled, neat, cable ties cut, cables secure.
-
List Items and Location to Items it Applies to
-
Fire stopping completed.
-
List Items and Location to Items it Applies to
-
Lighting plug and play connectors fitted
-
List Items and Location to Items it Applies to
-
Plot clear of materials, waste and swept out.
-
Snagging Issues
-
Snagging photos
-
Snagging items completed
-
Snags completed on
-
Completed snags
-
Comments and Feedback
-
Harrisons
-
Select date
-
Main Contractor
-
Select date
-
Handover completed