Initial Checks
-
Dynamic Rick Assessment Completed?
-
What PPE is being used?
-
What PPE is in use?
- Boots
- High Viz Jacket
- Hard Hat
- Fall Arrest Harness
- Gloves
- Mask
- Googles
- Overalls
- Ear Protection
-
Is additional PPE is required?
-
What is required?
-
Has all company vehicles been parked in a way not to cause a disruption?
Electrical Safety
-
All equipment has been PAT tested according to the policy?
-
Has a safe system of work been established? i.e. safe isolation?
-
Reduced voltage/ battery operated equipment is used where possible
-
Power cables are in good condition and located to prevent them being damaged or coming into contact with water
-
Test gear calibration checked and in date?
-
Other recommendations or observations?
Working at height
-
Is working at height part of the project?
-
Ladder Work
-
Defective or broken rungs/stiles/feet
-
The ladder is not fixed/tied and stable
-
Inclination is less or more than<br>roughly 4:1
-
Inappropriate choice of equipment for<br>the task
-
Inappropriate length for the task
-
Poor ground conditions (eg uneven /<br>soft ground / excess materials)
-
Other (eg over loaded / overreach to work area / resting on fragile or insecure surface / upside down, less than 3 points of contact)
-
Tower Scaffolding
-
Boards missing, damaged or<br>incorrect placement
-
Guardrails missing, damaged or<br>incorrect placement
-
Toeboards missing, damaged or<br>incorrect placement
-
Overhead hazards
-
Base of scaffold not locked in<br>position/poor ground/excess<br>materials
-
Outriggers/stabilisers missing or<br>damaged
-
Absent/insufficient safety and warning<br>signage (eg scafftags)
-
Other (eg inappropriate or missing internal access / inappropriate or missing material netting or guards / working outside the scaffold tower)
-
Step Ladders
-
The ladder is not fixed or tied and is stable
-
Defective or broken rungs/stiles/feet
-
Inappropriate height for the task
-
Poor ground conditions (eg uneven /<br>soft ground / excess materials)
-
Other (eg over loaded / overreach to work area / resting on fragile or insecure surface)
Site/ Customer
-
Is the site clean and tidy?
-
Have dust sheets been laid over floors where required?
-
Has a safe system of work been used to ensure the customer is kept safe?
-
Has consideration for other trades been made to ensure cooperation and safety of all on site?
-
Is the customer happy with the work taking place and understands what is involved?
-
Has the customer been walked through the job at the start?
-
Has the engineer used only one work zone at a time?
-
Has a safe zone been created for the customer?
Sign Off
-
Can the site be completed in a safe manner?
-
Is a further site visit required, to check for improved work practices?
-
When is a visit required
-
Is an off site meeting required to discuss finding on site?
-
What needs to be discussed, reasons for meeting? Please Detail.
-
Date for a meeting
-
Comments /Recommendations from this site visit?
-
Auditor
-
Auditor Position
-
Engineer 1:
-
Engineer Position
-
Engineer 2:
-
Engineer 3:
-
Date completed:
-
Engineer Comments