Title Page
To be completed by Maintenance technician
-
Factory
-
Asset No
-
Asset description
-
Work report
Work on the above machine has been carried out and the necessary repair/maintenance has been completed. No extraneous engineering debris, equipment or tools have been left on or around the machine. The machine has been left in a clean and tidy condition in preparation for hygiene/sanitation prior to being returned to production.
-
Signature
-
Date work carried out
To be completed by factory Manager/Supervisor
-
Cleaning procedure. Red - Do not start production until cleaning/sanitation has been completed.<br>Green - Check machine thoroughly and restart production if satisfied machine is clean.
-
I accept machine back after maintenance/repair and will ensure appropriate cleaning is carried out before returning it to production.
-
Date accepted