Title Page

  • Site inspected

  • Inspected on

  • Inspected by

  • Location
  • Row number

  • Table counted from West

Control section

  • Controlled by

  • Signature

Approve section

  • Approved by

  • Signature

Checks

  • SADEF structural drawings and assembly instruction are available on site and understood by installer?

  • Edge (unsheltered) and middle (sheltered) tables distribution is according to the layout plan?

  • Free distance below the lower panel is respected?

  • Immediately after ramming, head of pile (minimum the upper 2cm all around pile) is cleaned, and is repaired with 100 microns of zinc rich paint?

  • For all mutual holes in the connections between SADEF profiles corresponding bolts and nuts have been used?

  • Torque moment on bolts M8, M12 & M16 as specified by SADEF is respected?

  • If prescribed, all washers have been placed?

  • Table alignment is OK? (in longitudinal direction no shadow from one tablet to another?)

  • All parts (marks) on the SADEF structural drawing are mounted?

  • Panel alignment is OK?

  • Clamps sets are assembled following the SADEF clamp set summary (or Assembly Guidelines)?

  • Clamps are placed parallel to the PV panel?

  • Lateral gap between PV panel and clamp is lower than 2mm, and between 2 panels the max. distance is 21mm?

Overall Check

  • general opinion

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.