Title Page
-
Full address
- 149 Arran
- 147 Arran
- 145 Arran
- 139 Arran
- 131 Arran
- 125 Arran
- 121 Arran
- 119 Arran
- 117 Arran
- 113 Arran
- 109 Arran
- 101 Arran
- 100 Arran
- 93 Arran
- 92 Arran
- 90 Arran
- 89 Arran
- 88 Arran
- 87 Arran
- 82 Arran
- 80 Arran
- 77 Arran
- 76 Arran
- 75 Arran
- 74 Arran
- 73 Arran
- 71 Arran
- 70 Arran
- 69 Arran
- 65 Arran
- 64 Arran
- 63 Arran
- 60 Arran
- 56 Arran
- 48 Arran
- 42 Arran
- 40 Arran
- 38 Arran
- 36 Arran
- 34 Arran
- 32 Arran
- 22 Arran
- 20 Arran
- 12 Arran
- 10 Arran
- 8 Arran
- 6 Arran
- 5 Arran
- 4 Arran
- 3 Arran
-
Conducted on
-
Prepared by
-
Location
Work Type and Sign Off
-
Scaffolding Erection
- Scaffold erection complete
- Scaffold erected 1m below roofline
- All Scaffold clear of doorways
- Foam guards installed to standards at doorways
- Ladder access points installed
- Ladder access gates installed and working correct
- All Scaffold stop ends installed
- All toeboards and brick guards installed
- All Scaffold to be double handrailed
- Scaffold handover certificate received
- Supervisor sign off
-
INSPECTION COMPLETE
-
Chimney Repoint
- Chimney mortar raked out to 25mm in depth
- Chimney re-pointing works completed as per specification
- Brickwork cleaned of any excess mortar/ debris
- Snagging complete
- Supervisor sign off
-
INSPECTION COMPLETE
-
Strip Chimney Scaffolding
- Chimney scaffolding strip complete
- Any damaged tiles identified and replaced
- All scaffold materials removed from roof area
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
-
Roof Clean
- Roof clean complete
- All moss removed from roof area
- All moss removed from gutters after cleandown
- Scaffold left clean and tidy / all excess materials removed
- Ground area left clean and tidy / free from dirt
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
-
Soffit Removal
- Asbestos soffit removal works completed
- Any issues identified and communicated
- All materials removed from scaffold
- All ground areas checked / clean and tidy
- Removal certificate received
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
-
Soffit and Facia Install
- Soffit / Fascia replacement works complete
- Fixing spacing to Fascia at 450mm centres
- 75mm Polypin fixings installed at 50mm centres
- Joint strips installed and fixed
- Corner end caps installed and fixed
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
-
Rainwater Goods Install
- Gutter replacement works complete
- Gutter brackets fixed as per spec / spaced correctly
- Fall level correct
- All stop ends fitted / seals in place
- RWP installed
- RWP plumb, brackets installed and spaced correctly
- RWP installed correctly to drain outlet
- Water test complete
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
-
Scaffolding Strip
- Scaffold strip complete
- All areas clean and tidy
- All areas inspected
- Supervisor sign off
-
INSPECTION COMPLETE
-
Hedge Trim
- Hedges trimmed to correct height
- All trimmings removed and area left tidy
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
-
Fence and gate install
- Fence installation complete
- Gate installation complete
- Post spacing correct and plumb with correct spacing
- Fence line level free from damage
- Fixings per panel correct
- All gate furniture fitted and working correct
- Areas left clean and tidy
- Snagged
- Supervisor sign off
-
INSPECTION COMPLETE
Handover
-
Handed over to client