Title Page
-
Project Name
-
Location
-
Inspection Location
-
Date
-
Client
-
Project Manager
-
Prepared By
GASS FALSEWORK SYSTEM
-
TW design brief of GASS Falsework is in TW folder?
-
TW design check certificate of GASS Falsework is in TW file?
-
Which codes of practice used for design of GASS Falsework?
-
What category is the design?
-
Is TW drawing of GASS Falsework issued for construction?
-
Is TW construction drawing recorded in the TW register log?
-
Gass falsework-Erected as per construction drawing on site?
-
Are the main beams been positioned in the beam support centres of the prop heads?
-
Are the primary beams connection of GASS® T-bolt clamp (head to beam) used DU-AL™ T225 and T150 beams to GASS® leg. Two required per leg?
-
Are wedge clips placed on position?
-
Edge protection been installed?
-
Is TWS signed off the Gass falsework assembled?
-
Permit to access, load and strike issued and signed by TWC/TWS?