Title Page

  • Completed on

  • Completed by

  • Building Site

Building

  • Site drainage away from the house shall fall a minimum of 6 inches within the first 10 feet

  • Wood siding to be a minimum of 6” above adjacent grade

  • Building exterior finish to be completed

  • A 3’X3’ landing is required on each side of an egress door (some exceptions apply)

  • Garage to be separated from living space with minimum ½” gypsum wallboard on garage side

  • Door between house and garage to be a 20 minute rated door, a solid core 1-3/8” door or a steel clad insulated door

  • Enclosed accessible space under stairs is to be protected with ½” gypsum wallboard

  • Egress doors must be able to open from inside without the use of a key

  • Handrail height is to be 34” minimum and 38” maximum measured vertically from nosing of treads; handrails are required on stairs of 4 risers or more

  • Guardrails are to be installed on open sides of stairways, porches, balconies or raised floor surfaces more than 30” above the floor or grade below; finished height of guardrail is a minimum of 36”; open sides of stairways guardrail height may be reduced to a minimum dimension of 34” above the nosing of the stairs and a maximum of 38”

  • Foam plastic is to be separated from the building interior or crawl space by a thermal barrier of ½” gypsum wallboard unless tested and listed otherwise (except rim joists)

  • Install energy efficiency features & place completed energy sticker in electrical panel board

  • Final roofing material installed

  • Post permanent house numbers in location visible from the street

  • Under-floor areas to be cleared of all vegetation and construction debris

Electrical

  • Complete entire electrical system and install required fixtures

  • Smoke detectors installed and functioning

  • Interior wall surfaces to be installed to protect electrical conductors

  • Lighting fixture installed outside each exterior door

  • GFCI protected electrical outlets to be installed in kitchens, bathrooms, exterior (front & back), garage etc.

  • Electrical panel board covers on and circuit breakers identified for use

Plumbing & Mechanical

  • Heating system installed capable of maintaining 68 degrees 3 feet above the floor

  • Dwelling provided with a water closet, a lavatory and a bathtub or shower with a closeable door to the space

  • Dwelling provided with a kitchen area and sink

  • Dwelling provided with potable water to the building and DWV system tied to approved wastewater discharge system

  • Install pressure regulator at outfall of water meter (if street pressure >80 PSI) and thermal expansion tank on hot water system

  • Provide an air gap on the dishwasher drain line

  • Condensate lines for air conditioning and humidifier systems are to drain into the DWV system through an air gap

Sign Off

  • Name and Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.