Information

  • Client / Site

  • Quote No.

  • Conducted on

  • Prepared by

  • Personnel

Brief Job Description Details

  • Quote Ref:

  • Quotation has been read and installation requirements understood

  • Brief Description Of Work Carried Out.

Documentation/5 Part File Information

  • System Specification/Quotation Available?

  • System Category Specified?

  • List of Assumptions/Variations available and agreed by the client?

  • Pre installation battery design calc available?

  • Cable Test Results Available?

  • Design Certificate Available?

  • Installation Certificate Available?

  • Commission/Modification Certificate Available?

  • Mains Test Certificate Available?

  • Acceptance Certificate Available?

  • Was a Drawing Job Logged?

  • Updated Drawings and Zone Charts Completed?

  • Load Check Results Available?

  • Dual Com Signal Results Available?

  • Note any issues found with the above and document any documentation missing including the owner.

Site Related Audit (Health & Safety)

  • SSOW Available?

  • Did the engineer sign in and out of site (Check site log book*)

  • Asbestos register available and signed by engineer?

Quality of work carried out (Visual Inspection)

  • Has equipment been installed as per the specification/category and drawing requirements?

  • Have the devices been correctly numbered and dotted?

  • Has the correct cabling been used?

  • Has suitable containment been installed?

  • Has the cable been mechanically protected where required?

  • Has the cable been correctly fitted to the containment and segregated where required?

  • Have cable holes been fire stopped?

  • Are any cable joints suitably terminated and boxes labelled?

  • Has suitable mains been provided using a dedicated circuit and double pole isolator fitted adj. all equipment?

  • Is the mains supply independent of any RCD protection?

  • Has the mains been correctly labelled?

  • Has suitable mains cable been used and segregated from the other fire system low voltage cabling?

  • Do mains supply cables enter the control equipment separately?

  • Have batteries been date labeled correctly?

  • Do other mains supplies to external PSU's meet the above criteria?

  • Is there suitable short circuit isolation specified? (Addressable systems)

  • Are there at least 2 Sounder circuits?

  • Are there sufficient quantity of MCP's taking into account maximum search distance?

  • Are call point location and siting appropriate?

  • Are call point mounting heights correct?

  • Are suitable IP rated devices fitted where required?

Practical Commissioning Checklist

  • All manual call points and detection devices function correctly

  • Do call points still operate if a detector is removed?

  • Is an evacuate signal sounded within 3 seconds of call point activation?

  • Both elements for multi sensors tested

  • Beam detection tested at receiver or reflector end

  • Devices operate the correct zonal indication in accordance with the zone chart and zoning is adequate?

  • Sound pressure levels checked and recorded

  • Fire and fault signals to ARC tested

  • Cause and effect requirements function correctly

  • All input and output interfaces operate correctly

  • Load test completed and results recorded

  • Control panel functions and indicators operate correctly

  • Open/short circuit faults have been simulated on all circuits

  • Detector removed fault indication/diodes checked (conventional circuits)

Monitoring

  • Has a suitable EN54 PSU been installed?

  • Is the PSU fault monitored?

  • Is the wiring from the transmitter to the fire system monitored?

  • Has the monitoring been fully tested and gold commissioning standard acheived?

PDA/ Docket Report Information

  • Engineer report available with sufficient detail?

  • Has the engineer documented that the equipment installed has been tested and is operational (*critical process)

  • Has the site log book been completed?

Handover. Have the following been supplied to the client?

  • Relevant certification as listed in the 5 part file requirements

  • Fitted Zone Chart

  • As Fitted Drawings

  • O&M Manual

  • Log Book

  • Customer training completed and documented

Audit Report Summery

  • Audit Summery (Document any corrective action that needs attention, office or site related)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.