First Work Inspection - Stucco
-
The Clayton
-
Conducted on
-
Prepared by
-
Select date
General Information
-
Project
-
Building
-
Level
-
Area
Field Checklist
-
Insure the lath at control joints is continuous - ie wired to lath.
-
Insure the lath is discontinuous at expansion joints.
-
Insure scratch, brown, and finish coats are applied per manufactures recommended thickness.
-
Insure that the drainage plane is properly integrated with the adjoining flashings, membranes, and sealants.
-
Insure that kick-out flashings are not sealed.
-
Insure that moisture levels are measured, recorded, and are consistent with manufacturers recommendations before applying subsequent coats of material.
-
Insure that bottom of stucco system is the specified distance above grade - per code.
-
Insure that all penetrations are adequately flashed/sealed prior to covering.
-
When completing the finish coat - insure that an entire elevation is completed at the end of the day - interruptions may cause differences in color and texture.