Information
-
Site
-
Conducted on
-
Prepared by
-
Contractors On Site
Site Arrival
-
JSA filled out properly
-
Proper warning signs posted at entrance
-
All personnel in proper PPE
-
Location has designated smoking area
-
Additional Comments
Tree
-
Consultant
-
Flanges have all bolts and are the correct size and properly torqued and tested
-
All valve handles are correctly installed for proper use
-
Valves capable of venting to atmosphere are capped & a means of bleed off installed.
-
Tree pressure tested at shop to maximum anticipated pressure/ API standard
-
Verify that the # of turns to (FULLY) open/close each valve and choke are written on the wellhead and are correct
-
Additional Comments
Flow Lines
-
Flow back hand
-
No threaded connections upstream of choke manifold
-
All flow iron upstream of choke must be tested to 10k and 5k downstream of choke banded/identified every 6 months
-
Minimize the use of threaded connections
-
Break apart ALL threaded connections and visually inspect before EVERY flow line installation
-
Tested to maximum anticipated pressure + an acceptable safety margin or working pressure
-
Unions are positioned correctly for direction of flow & checked for compatibility
-
Lines are not bowed or laid in a bind
-
Block tees are supported
-
Additional Comments
Flow Line Anchors
-
Flow Back Hand
-
Set as not to cause excessive dips, arches, or bows in flow lines
-
Set first anchor as close to wellhead as feasible placing one every joint- upstream of manifold every other joint- downstream of manifold with hammer union positioned between the anchors
-
When encountering bend or turn in flow line repeat process placing first one as close as feasible after turn with one every other joint thereafter
-
Verify that anchors have been driven flush to the top of line clamp (NO USE OF SUCKER RODS)
-
Verify that the clamps used with the anchors are correct size for the outside diameter of flow line
-
Verify that clamps/anchors are sufficiently bound together and annotate be broken apart
-
Insure that anchor clamps are 1/2" thick by 3" wide by 12" length with rod holes no greater than 1" or equivalent
-
Additional Comments
Manual Chokes
-
Consultant
-
When completely closed- reading is 0/64
-
Pressure test body to same pressure as flow line
-
Housing and seat checked prior to flowing of we'll
-
Additional Comments
Sand Separator (if applicable)
-
Flow Back R/U Crew
-
Set in level position
-
Valves and related components function tested prior to flow back operations
-
All flanges contain correct nuts and bolts
-
Cleaned out prior to installation
-
Tested to maximum anticipated pressure plus and acceptable safety margin - if installed upstream of choke
-
By-pass installed and tested to system pressure
-
Additional Comments
Flow Back Separator
-
Flow Back R/U Crew
-
Set in level position
-
Adequate fall protection of tie-offs Built in or portable platforms if properly secured will suffice)
-
Valves checked prior to flow back and function tested at appropriate time.
-
Additional Comments
Flow Back Tank/ Gas Buster
-
Tank Company
-
Clean sand prior to transport
-
Set level
-
Adequate fall protection or tie-offs(built in or portable platforms if properly secured will suffice)
-
Easy access for tank gauging, walkways and stairs should not be damaged or missing pins
-
External valves not in use have barrier device installed in case of accidental opening
-
Set to provide easy truck access for hauling out produced fluids
-
Working wind sock installed near tank
-
Additional Comments
Compressed Gas
-
Company Delivering Cylinder
-
Bottle secured (preferred bottle rack)
-
Bottle labeled properly as to contents
-
SDS available on site
-
Additional Comments
Flare Line
-
Flow Back R/U Crew
-
Should be laid in straight line. Direction change must be made with appropriate connection. All attempts must be made to cut down on direction changes.
-
Flanges have all bolts installed and uniformly tightened (no 1/2 nuts)
-
Line should extend 100 ft. From combustible source
-
Flare stack minimum of 6 inch OD with proper ignition system. Any changes must be per approved by Superintendant
-
Additional Comments
H2S
-
EHS Specialist
-
H2S plan provided for well that may exceed 10 PPM
-
H2S site specific procedures developed for location (if required)
-
H2S contingency plan on location (if required)
-
H2S plan is coordinated by safety department and implemented by foreman
-
Foreman on site
-
Additional Comments