Title Page
-
Lasail
-
Conducted on
-
Prepared by
-
Site Name & Client
-
Location
Scaffold Deck Photos taken in 10 step increments.
-
Scaffold Base Photos
-
Scaffold Deck #1 Photos
-
Scaffold Deck #2 Photos
-
Scaffold Deck #3 Photos
-
Scaffold Deck #4 Photos
-
Scaffold Deck #5 Photos
-
Scaffold Deck #6 Photos
-
Scaffold Deck #7 Photos
-
Scaffold Deck #8 Photos
-
Scaffold Deck #9 Photos
-
Scaffold Deck #10 Photos
Monthly Inspection
Handover/Inspection:
-
Docket No
Scaffold Inspection
-
Lead Hand:
Scaffold Design #:
-
undefined
Supporting Structures/Foundations
-
Are the Base/sole boards fully supported by the foundation?
-
Are all working deck boards installed?
-
Are all sole boards visible for inspection?
-
# of Wall and Raker ties. (Upload photo of Site register)
-
Have a minimum of 10% of ties been checked per level?
-
Is any part of the scaffold built from other than ground, Spurs/Needles?
-
Are Needles/Spurs installed as per design & swms?
-
Are jacks/Uheads sitting square on footing or support?
-
are the set hop ups within 300mm above or below slab?
-
Does the supporting structure continue to have adequate strength?
-
Are ALL kickboards in place and secure?
-
Is unimesh/ Chain & Shade Installed to ALL live decks?
-
Is safe access and egress provided to all working platforms?
-
Are overlapping boards secured where required in the 2021 QLD COP?
-
Are Stairs and Ladders installed correctly and has mesh been lapped minimum 200mm?
-
Is ALL Access/Egress ways clear of hazards? ( building materials, loose scaffold components)
-
Has the PCBU or other trades got any items stored on the scaffold that need to be removed immediately?
-
Are maximum Loads displayed on Loading bays top and bottom?
-
Is there sufficient signage or barriers to incomplete scaffold?
-
Are Specialised scaffold designs erected according to design and swms?
-
Is there a scaffold tag in place and has it been updated to this Inspection?
-
Are any Corrective Actions required? (e.g. request Manager Audit)
-
I certify that I have performed the Monthly inspection and find the scaffold has been erected to and or remains to conform to the prescribed aforementioned standards.
-
Signed:
-
The Scaffold did not pass the inspection and cannot be handed over until corrective action has been completed and the scaffold has been re-inspected
-
Client Representative Name:
-
Signed:
-
Do you take receipt and acceptance on behalf of principle contractor?
-
Date: