Title Page
-
Site conducted
-
Location
-
Conducted on
-
Prepared by
Safety Checks
-
Weather conditions
- Fair
- Hot
- Cold
- Sunny
- Cloudy
- Frosty
- Rainy
- Windy
-
Are set Boundary set back measurements correct?
-
Have plumbing and electrical conduits been installed?
-
Are they installed within a bracing element?
-
Is there an earth bar installed on the electrical conduit?
-
Does this foundation require any shower recesses?
-
Are they the correct size and location?
-
Are all joinery recesses installed as per plan?
-
Are all brick rebates installed as per plan?
-
Have buckets been installed on all wastes?
-
Are all garage rebates installed?
-
Is the boxing bracing satisfactory?
-
Are all Thickenings installed as per engineer plan?
-
Have all weld plates/cast in bolts been installed?
-
Is the site tidy?
-
Has the council and engineer inspections passed?
-
Has the BLC been issued?
-
Are there any obstructions for the concrete trucks/ pump?
-
Any further observations?
-
Photos of foundation and site (10 minimum)
-
Is boxing to height?
-
where is it out of level?