Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Wind Speed
-
Are piers in compliance with the NCC Figure 3.3.1.6?<br><br>Note: If over 1500, piers must be increased to 350mm@base below 1500mm.
-
Are bearer tie-downs in place?
-
Is floor structure as per plan?
-
Have floor joists been blocked in accordance with AS1684 Section 4.2.2.3?<br><br>Note: If joists are >4x the width of the stud blocking is required over all bearers.
-
Has truss design criteria been supplied from supplier and is the construction in compliance with these plans?
-
Have all rafters been tied to top plates using cyclone straps?
-
Has a plan been received from the supplier for any prefabricated beams/wall frame & is the construction in compliance with these plans?
-
Have lintels been installed as per plan?
-
Is wall bracing as per plan?
-
Is nailing patter correct for the bracing type - See AS1684
-
Have steel braces been installed correctly: min 1800L-2700L maximum?
-
Have racking forces been transferred around all bracing walls (including ply braces) in accordance with AS1684.2-1999, tables 8.22 & 8.24?
-
Are window openings over 900mm strapped at all 4 corners & tie-downs been installed either side through bottom plate to floor structure below?
-
If softwood, have double studs been installed either side of window openings?
-
Are any rafters/trusses hitting top plate & more than 52.5mm away from the studs? If so, have noggings been installed under top plates?<br><br>Note: Not required for double top plates.
-
Are rafters and sizes as per plan?
-
Is minimum clearance under all bearers 150mm minimum?
-
Have galvanised fixings been installed to treated pine members?
-
Is roof pitch 5 degrees minimum?
-
Does general layout check confirm likely compliance with the plans?
-
Are windows as per plan?<br><br>Note: Alterations may affect glazing calculations for thermal efficiency.
SIGN OFF
-
On Site Representative
-
Building Surveyor
-