SLAB

  • Are the overall slab dimensions as per plan

  • Has the slab an even surface

  • Is the slab surface clean of chalking

  • Photo if required

MASTER BEDROOM and WIR

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Have studs been placed at 300cts at end of WIR

  • Photo if required

BEDROOM 2

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Photo if required

BEDROOM 3

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Photo if required

BEDROOM 4

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Photo if required

STUDY

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Photo if required

LIVING ROOM

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Photo if required

KITCHEN , DINING AREA

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Have pluming wastes been located correctly

  • Photo if required

PANTRY

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Have pluming wastes been located correctly

  • Photo if required

LAUNDRY

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are door dimensions correct width and height

  • Have pluming wastes been located correctly

  • Photo if required

BATHROOM

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are wastes and plumbing located in correct positions

  • Is shower box located correctly and studs placed at 300cts around shower

  • Are door dimensions correct width and height

  • Are neich's placed in correct position and correct size

  • Photo if required

MASTER ENSUITE

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Are wastes and plumbing located in correct positions

  • Is shower box located correctly and studs placed at 300cts around shower

  • Are door dimensions correct width and height

  • Are neich's placed in correct position and correct size

  • Photo if required

GARAGE

  • Are all room dimensions as indicated on plan

  • Have studs been placed under loads

  • Have all ceiling plaster trimmers and change of direction trimmers been installed

  • Are all internal corners plumb and level

  • Has bracing been placed as per engineers

  • Have garage door ceiling blocks been installed

STAIR VOID AND ENTRY VOID

  • Do all lower walls line up straight to upper walls

  • Are all void dimensions as per plan

GENERAL POINTS ON FRAME

  • Overall quality of frame

  • This frame has been inspected by

  • The frame items have been completed by

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.