Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Select date
SLAB
-
Are the overall slab dimensions as per plan
-
Has the slab an even surface
-
Is the slab surface clean of chalking
-
Photo if required
MASTER BEDROOM and WIR
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Have studs been placed at 300cts at end of WIR
-
Photo if required
BEDROOM 2
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Photo if required
BEDROOM 3
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Photo if required
BEDROOM 4
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Photo if required
STUDY
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Photo if required
LIVING ROOM
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Photo if required
KITCHEN , DINING AREA
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Have pluming wastes been located correctly
-
Photo if required
PANTRY
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Have pluming wastes been located correctly
-
Photo if required
LAUNDRY
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are door dimensions correct width and height
-
Have pluming wastes been located correctly
-
Photo if required
BATHROOM
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are wastes and plumbing located in correct positions
-
Is shower box located correctly and studs placed at 300cts around shower
-
Are door dimensions correct width and height
-
Are neich's placed in correct position and correct size
-
Photo if required
MASTER ENSUITE
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Are wastes and plumbing located in correct positions
-
Is shower box located correctly and studs placed at 300cts around shower
-
Are door dimensions correct width and height
-
Are neich's placed in correct position and correct size
-
Photo if required
GARAGE
-
Are all room dimensions as indicated on plan
-
Have studs been placed under loads
-
Have all ceiling plaster trimmers and change of direction trimmers been installed
-
Are all internal corners plumb and level
-
Has bracing been placed as per engineers
-
Have garage door ceiling blocks been installed
STAIR VOID AND ENTRY VOID
-
Do all lower walls line up straight to upper walls
-
Are all void dimensions as per plan
GENERAL POINTS ON FRAME
-
This frame has been inspected by
-
The frame items have been completed by