Title Page

  • Audit Title

  • Clients Name and Lot Number

  • Conducted on

  • Prepared by

  • Location
  • Name: LBP Or Registered Applicator.

  • Registration Number:

Documentation

  • Producer Statement Required ?

  • Exposure Zone Correct ?

  • Consent Approved Products Used ?

  • Installation Warranty Required ?

  • Framing / Wraps And Cavity Inspections Completed ?

  • Type

  • Installers Name

  • Elevation:

  • Balcony / Decks - With Adequate Fall And Overflow Drains ?

Documentation Comments

  • Comments.

  • Consent Number:

  • Date:

Roofing

  • Roofing Integrity

  • Down Pipes (Size And Fixing)

  • Internal Gutters

  • Flashings

  • Outlets

  • Roof Slope

  • Kick Outs

  • Fixings

  • Spouting Clearance

  • Spreaders

  • Penetrations

  • Overflows

  • Roofing Complete

Brick Veneer

  • Type

  • Sealer Sighted At Rebate

  • Ties

  • Tape Required For Studs (Over 450mm)

  • Weep Holes And Vents Every 4th Vertical Joint

  • Lintel /Shelf Angles Supports And Fixings.

  • Seismic Joints / Slip Joints

  • Pipes And Services Clear From Cavity

  • Flashings Correctly Installed (Windows, Doors, Kick Outs, Roofs, Parapets, Decks, Chimney)

  • Meter Board Flashings

  • Ground Clearance, (Measure In mm)

  • Sealing Of Penetrations

  • Cavity Clean

  • Cavity Size (Measure In mm)

  • Junctions - Wall To Wall & Wall To Roof

  • Gable Studs At 450mm Centres

Metal Cladding/ Weather Boards

  • Type

  • Cavity Base And Ventilation

  • Flashings Correctly Installed (Windows, Doors, Roofs, Parapets, Decks, Chimney)

  • Meter Board Flashings

  • Clearance Behind Fascias, Barge, Facing, Spoutings Etc (20mm Minimum)

  • Correct Clearance At Roofs, Decks (35mm minimum)

  • Measurement in mm

  • Capillary Gap Behind Cladding (6mm Minimum Measurement)

  • Measurement In mm

  • Adequate Ground Clearance

  • Measurement In mm

  • Sealing Of Penetrations

  • Differing Cladding Junctions

  • Consent Number

  • Date

  • Solid Plaster System

  • Proprietary Plaster System

  • First Coat

  • Second Coat

  • Type:

  • Appropriate Foundations

  • Tape Required For Stud (Over 450mm)

  • Substrate (RAB) Fixed To Manufacturer's Specifications.

  • Bracing Panel Fixings Installed

  • Cavity Base And/Or Head Ventilation And Vermin Protection (Cavity Closer)

  • Correct Reinforcing Materials And Reinforcing To Corner Of Openings

  • Reinforcing Overlaps, Spacing From Substrate And Fixing

  • Jointing To Manufacturer's Specifications

  • Control / Expansion Joints - Vertical And/Or Horizontal (4mm Maximum)

  • Flashings Correctly Installed (Windows, Doors, Roofs, Parapets)

  • Meter Board Flashings

  • Sealing Of Penetrations- Electrical Cables Sleeved

  • Clearance Behind Fascias, Barge, Facings, Spoutings, Etc. (20mm Minimum)

  • Correct Clearance At Roofs, Decks (35mm Minimum)

  • Measurement In mm

  • Capillary Gap Behind Cladding (6mm Minimum)

  • Measurement In mm

  • Adequate Ground Clearance (Measure)

  • Measurement In mm

  • Reveals/Facings To Joinery Of Face Sealed Cladding?

  • Junctions- Wall To Wall and Wall To Roof

  • Drip Edge

  • Gable Studs At 450mm Centres

  • Specify Area Checked

  • Specify Items Checked

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.