Information
-
Document No.
-
Electrical Underground Conduit Inspection
General
-
Time
-
ITP Inspection
-
Inspection Type
- Clear & Grub
- Strip Topsoil
- Excavation
- GST
- Subgrade / Unbound Pavement
- Trenching
-
Basic Location
- Access Roads
- EPCM
- Overland Conveyor
- ROM Reclaim
- ROM Transfer Pad
- MIA
- Raw Coal Stockpiles
- CV-045
- TS-044
- CV-008
- General Surface Aress
- MSF
- M&M Drift
- Mainteck Offsite Yard
- CV Drift
- SK041 RCS Stacker
- RE041 RCS Reclaimer
- Substation MP-SU-422
- Substation MP-SU-444
- Substation G1-SS-H01
- Substation G1-SS-A01
- CHPP
-
Specific Location/s
-
Attendees
- Mark Sanders
- Bruce Johnston
- Wylie Pearson
- David Seaver
- Mal Pringle
- Phil Adlam
-
Other Attendees
Inspection
-
Underlying Lots Closed
-
Add notes
-
Add photos
-
Services and permits in place
-
Add notes
-
Add photos
Trenching
-
Trench according to drawings
-
Add notes
-
Add photos
-
Bottom of trench compaction >95%
-
Add notes
-
Add photos
Service Installation
-
1. Bedding Material Complies with specification
-
Add notes
-
Add photos
-
2. Conduit Installation complies with spacing requirements
-
Add notes
-
Add photos
-
3. Hard Cover Protection Installed Correctly
-
Add notes
-
Add photos
-
4. Survey Pickup complete
-
Add notes
-
Add photos
-
5. Back filling carried out in accordance with specifications
-
Add notes
-
Add photos
-
6. Back Fill compaction complies with specifications
-
Add notes
-
Add photos
-
7. Are cable route markers installed
-
Add notes
-
Add photos
-
8. As built survey complete
-
Add notes
-
Add photos
Signoff
-
Inspector
- Mark Sanders
- Bruce Johnston
- Wylie Pearson
- David Seaver
- Mal Pringle
- Phil Adlam
-
Signature