Frame Checklist Ground Floor

  • Frame installation in accordance to layouts/shop drawings

  • Frame tie down in accordance to layouts/Aus standards ie Dynabolts every 1200mm where there isn't rods

  • Frame nailed/screwed off in accordance to Aus standards 2,2,2

  • All ply/strap brace nailed/screwed off in accordance to Aus standards 2 nails/screws per stud

  • All internal and external frames are within 5mm plumb/straight

  • All frames are in position as per plans/shop drawings

  • All door openings have been cut out and finished off neatly

  • All frames have gang nails/tripple grips on top of plates as per layouts/Aus standards

  • All joists are installed in accordance to layouts/Aus standards

  • Insure all joists are shoot/screwed off 3 nails/screws per joist

  • Insure all joist blocking is installed as per layouts/Aus standards

  • Insure all beams/steel is installed as per accordance to layouts/Aus standards

  • Insure all joists have boots/grips screwed in accordance to Aus standards 4 into beam/steel 4 into joist

  • Insure all joists are trimmed out for gyprock

  • Insure all windows are installed straight and plumb batten where brickwork pack where hebel and cladding

  • Insure job site is clean and tidy at the end of ground floor completion

  • Install all steel beams/columns

  • Install all chemset dynabolts to all steel posts

  • Install all bolt connections for timber infill beams

  • Install all lower frame tie down rods

  • install lower roof box gutters will fall

  • Bathroom blocks on lower level

  • Strap window/door openings 1 strap if under 1800 2 straps if over 1800

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.