Title Page

  • Tenants Name (from lease)

  • Tenants Address (from lease)

  • Tenancy Unit Number

  • Centre Name

  • Trading Name

  • Lease Number

  • Conducted on

  • Prepared by

Landlord works

  • Actual handover of the above premises occurred today.

    Landlord's works have been completed except for:

  • Minor matters that will not prevent the Tenant from conducting Fitout Works

  • Please provide details

  • Matters that will be affected or require interface with the Tenant's Fitout Works

  • Please provide details

Signatures

  • Signed for and on behalf of the Landlord:

  • Acknowledged by/for and on behalf of the Tenant:

Tenancy Condition

Tenancy Condition

  • Tenancy Floor - Timber or Concrete smooth finish

  • If No - please provide details

  • Notes

  • Mall Tile Ingo - Completed and cut to lease line

  • If No - please provide details

  • Notes

  • Drainage Supply Point - Installed and position OK

  • If No - please provide details

  • Notes

  • Water Supply Point - Installed and position OK

  • If No - please provide details

  • Notes

  • Gas Supply Point - Installed and position OK

  • If No - please provide details

  • Notes

  • Exhaust Supply Point - Installed and position OK

  • If No - please provide details

  • Notes

  • Tenancy Clean - Cleaned and Acceptable

  • If No - please provide details

  • Notes

  • Temp Electrical Distribution Board (EDB) - Installed to rear wall

  • If No - please provide details

  • Notes

  • Temp Electrical Distribution Board (EDB) - Installed to rear wall

  • If No - please provide details

  • Notes

  • Electrical Supply Main Cable - Installed to rear wall with 5m slack coiled in ceiling area

  • If No - please provide details

  • Notes

  • Comms Main Cable - Installed coiled in ceiling area

  • If No - please provide details

  • Notes

  • Thermostat and Cable - Installed coiled in ceiling area (documented on drawing for new installation location.

  • If No - please provide details

  • Notes

  • Sprinklers - To open plan

  • If No - please provide details

  • Notes

  • Air Conditioning - To open plan

  • If No - please provide details

  • Notes

  • Additional Builders Works - Are Works completed

  • If No - please provide details

  • Notes

Lessee's Responsibilities (New Tenant)

  • Pre Start Meeting - Completed

  • Notes

  • Schedule D - Completed

  • Notes

  • Building Permit - Received

  • Notes

  • Design Approval Granted - Final Documentation Drawings Provided

  • Notes

  • Shopfitter Inductions - Completed

  • Notes

  • Fitout Program - Received

  • Notes

  • Category One Works - Approved / Accepted

  • Notes

  • Supply Authorities - Contacted

  • Notes

Pre-Trade Requirements

  • Leases Signed

  • Notes

  • Bank Guarantee

  • Notes

  • Public Liability Insurance (PLI)

  • Notes

  • Category One Works Paid

  • Notes

  • 1st Month's Rent Paid

  • Notes

  • Opening Promo Paid

  • Notes

  • Design Review Fee Paid

  • Notes

  • Hoarding Fee Paid

  • Notes

  • Major Defects Rectified

  • Notes

  • Final Trade Certificates and Certificate of Final Inspection (Occupancy Certificates) Recieved

  • Notes

Absentee Handover

  • NOTICE OF ABSENTEE HANDOVER OF PREMISIS

    We advise that handover of the above premises occurred on:

  • Select date

  • We note that you chose not to have a representative present at handover.

    We attach the following for your information only.

    a) Notice of Actual Handover; and
    b) Handover Site Status Photographs

    Your lease will commence on expiry of the fitout period, or on the commencement of trade, whichever is the earlier.
    If you have not already done so, we remind you that prior to commencing any works on site you must:

    o ensure that your design drawings have been received final design approval by your Vicinity Retail Design Manager and the relevant authorities;
    o ensure that your Building Permit has been forwarded to the Fitout Coordinator at Centre Management; and
    o arrange for your shopfitter to undertake a site induction.
    If you have not already done so, we remind you that prior to the commencement of trade you must:

    1) return your executed lease documents to our solicitors, Minter Ellison;
    2) provide your Bank Guarantee to your Credit Officer;
    3) provide your certificate of currency of insurance for $20 million to Centre Management;
    4) provide your rent in advance to your Leasing Executive;
    5) pay your hoarding charges (if applicable);
    6) pay the Design Review Fee;
    7) pay the Category 1 charges (if applicable) (note the charges will be provided to you on handover of the tenancy);
    8) rectify defects in your shop fitout; and
    9) otherwise comply with all other terms of the lease documents.

    Please note that failure to complete any of the above will not delay your lease (and rental) commencement date, but will prevent you commencing your fitout works or commencing trade.

  • Photos of Tenancy Condition at Handover

  • Signed for and on behalf of the Landlord:

Schedule D

  • SCHEDULE D

    ACKNOWLEDGMENT OF REQUIREMENTS

    • Please complete and return this form to Centre Management as soon as possible.
    • Work will not be permitted to commence until this form is received.
    • Please contact the required contractors in advance of the fitout and allow ample time in scheduling of shop fitout for these services to be carried out.

  • Shopfitters/Contractor I,

  • Of,

  • Shopfitters/Contractor working on shop number:

  • In Shopping Centre:

  • acknowledge that I have read and understand The Guidelines for Tenancy and Centre Works of Vicinity Centres as per the attached document.

    I also agree to comply with these guidelines and will ensure that my employees, contractors and visitors
    during the fitout or works period undergo an induction so that they understand the requirements, the risks
    posed by the operations being conducted at the site and the risks and safety procedures for the Centre.

  • Signature of SHOPFITTER/CONTRACTOR

  • TENANT I,

  • Of,

  • being the Tenant of shop number

  • In Shopping Centre:

  • acknowledge that I have read and understand the requirements of Vicinity Centres as per the Guidelines for Tenancy and Centre Works documentation.

    I agree to comply with the guidelines and will ensure that my employees, contractors and visitors during the
    fitout or works period undergo an induction so that they understand the requirements, the risks posed by the
    operations being conducted at my tenancy and the risks and safety procedures for the Centre.

  • Signature of TENANT

  • Authorised by: Centre Operations Manager or Centre Manager

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.