Title Page

  • Site conducted

  • Conducted on

  • Prepared by

  • Location

PROJECT:

  • Project

  • Location

  • Site

VERIFICATION:

  • 1. Correct Plant for use .

  • 2. Correct Plant delivered

  • 3. Damage to Plant

MOUNTING OF PLANT:

  • Plant location as per drawing

  • Correct mounting brackets used

  • Correct material used

  • 2. Pipe brackets as required

  • 3. All pipework completed in area

  • 4. All pipe work pressure tested

CONNECTING OF PLANT TO WATER SUPPLY AND HOT WATER SYSTEM:

  • 1. Correct material used

  • 2. Pipe brackets as required

  • 3. All drains connected

  • 4. Drained to approved location

  • CONNTROL PANNEL:

  • 1. Control panel mounted in accessible location

  • 2. Control panel securely fixed

  • 3. Power supply connected to panel

COMMISSIONING:

  • 1. Plant commissioned by supplier

  • 2. Water supply turned on

  • 3. Electrical supply turned on

  • 4. All valves in operating position

  • 5. All pressure gauges working and visible

  • 6. Correct ventilation requirements in room

  • 7. Plant operating correctly

  • Checked by

  • Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.