Title Page

  • Site conducted

  • Plot Number

  • Conducted on

  • Prepared by

  • Location

1. Foundation

  • 1. Foundation/substructure and ground floor, to show thermal continuity and quality of insulation In the following places.

  • Ground Floor Perimeter edge Insulation

  • At External Front Door threshold

  • Below add photos of additional individual door locations

  • Additional Foundation Door location photos
  • State Door Number or location

  • Photo of Insulation at Door threshold

  • Photos of below Damp-proof Course on external walls (Cavity)

2. External walls

  • For each main wall type, to show thermal continuity and quality of insulation for the following.

  • a. Ground floor to wall Junctions. B. structural penetrating elements ( extractor ducts and boiler flues at 1st fix in timber frame)

  • NOTE: for blown fill, photos should show clean cavities and clean brick ties with very limited mortar droppings

  • External wall Photo
  • Location Description

  • Photo

3. Roof

  • For each main roof type, to show thermal continuity and quality of insulation at the following.

  • a. Joist / rafter level/ b. eves and gable edges

  • Roof Photo
  • Location Description

  • Photo

4. Openings

  • For each opening type (one image per wall or roof type is sufficient}, to show thermal continuity and quality of insulation with photographs of the following.

  • a. Window positioning in relation to cavity closer or insulation line/ b. externals door set positioning in relation to cavity closer or insulation line

  • Window Opening
  • Window Location

  • Photo

  • Door Opening
  • Door Location

  • Photo

5. Airtighness

  • Additional photographs for all details 1-4 to show airtigrtness details (only if not included or visible in continuity of insulation image).

  • Airtightness Photo
  • Location/ item description

  • Photo

6. Building services

  • For all plant associated with space heating, hot water, ventilation and low or zero carbon technology equiptment within or on the building, show the following

  • A. Plant/ Equipment identification label(s) including make/ model and serial number. B. Primary Pipe Work continuity of Insulation. C. Mechanical ventilation duct work. D. Continuity of Insulation of Insulation (For Ductwork sections outside of the Thermal envelope (loft space)

  • Mechanical Ventilation Ductwork
  • Which room is this duct for?

  • Photos of duct install.

Primary Pipe work

  • Photos showing primary pipe work fully lagged

Plant / Equipment (Heating, Hot Water, Ventilation)

Hot water System

  • Photographs should show position of the hot water system, with labels clearly identifying make and model of the system

Heating System

  • Photographs should show position of the equipment, with labels clearly identifying make and model of heating system

Ventilation System

  • Photographs should show position of the equipment, with labels clearly identifying make and model of ventilation system

  • Low Carbon Technology (PV panels, Invertor, ASHP etc)
  • Photographs should show position of the equipment, with labels clearly identifying make and model of the systems installed

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.