Title Page
-
Date of Audit
-
Scope the audit
-
Prepared by
General Information
-
Score Ranking
-
Evaluation Chart
-
All the items with Class III score must be defined at least one corrective action.
-
In the items with Class II & III score should be added a evidence or the issue description
A) O&M general Activities
1.0 Audit Description
-
1.1 Describe the general activities audited on site
-
1.2 Name of O&M company supervisor
2.0 Audit report
-
Add an audit report for each activity audited on site
Activity audited
-
If the result of the next points are unsatisfactory (2.4, 2.12, 2.15) must be marked each option as Class III failed reponse
-
2.1 Describe the specific task audited on site
-
Describe the specific task to be audit by the Services company
-
2.2 Name of the serivces company audited
-
2.3 Description of the area audited
-
2.4 Se dispone de permiso de trabajo/ It is available the work permit on site
-
2.5 Existe plan de seguridad/evaluación de riesgos/ the HS Plan or Risk Assesment is available and updated on site
-
2.6 La documentación de seguridad se encuentra correcta y actualizada/ The safety documentation (paperwork) is correct and updated
-
2.7 La zona de trabajo se encuentra señalizada con los riesgos existentes/ The work area is signed with the main risks
-
2.8 Los huecos, aberturas, o desniveles se encuentran correctamente protegidos, con barandillas, barreras, etc./ the holes and gaps are protected properly with handrails, barriers, etc.
-
2.9 El vallado o cierre perimetral de la instalación se encuentran en buen estado/ The installation of the perimeter fence is in good conditions
-
2.10 Se hace uso de maquinaria con marcado CE, en buenas condiciones de mantenimiento y limpieza/ The machinery is marked with CE label, and is maintained properly
-
2.11 La maquinaria dispone de las revisiones o inspecciones periódicas correspondientes/ The machinery has the checks and inspections updated
-
2.12 Los equipos disponen de protecciones y la señalización adecuada/The work equipment has the proper safeguards and signaling
-
2.13 Se dispone y se hace un uso correcto de los equipos de protección individual/ the ppe´s are available and the workers are using the ppe´ss properly
-
2.14 Los equipos se encuentran revisados/ The ppe´s are checked
-
2.15 Se hace uso de los equipos correctamente de acuerdo a los riesgos existentes/ The workers are using the ppe´s in according to the risks involved to this area
-
2.16 La zona de trabajo se encuentra en buen estado de orden y limpieza/ The work area is in a good conditions respect to order and cleaning
-
2.17 Las vias de paso y emergencia se encuentran libres de obstáculos/ The route or transit and emergency areas are free of obstacles
-
2.18 Los productos químicos se encuentran en sus recipientes y etiquetados correctamente/ The hazard substances are in their containers and signed properly
-
2.19 Existe un correcto orden y almacenaje de los productos/ There is a proper housekeeping and storage of the chemical products
-
2.20 Se hace un uso correcto de los productos de acuerdo a las instrucciones del fabricante/ The chemical product are using in according to the manufacture instructions
-
2.21 Se disponen, y se encuentran en buen estado los equipos de emergencia, rescate y evacuación/ It is available, and in a proper conditions, the emergency, rescue and evacuation equipments
-
2.22 Existe señalización de los equipos, medios de emergencia y evacuación/ There is a proper signaling of the emergency equipments
-
2.23 Se realiza un correcta limpieza y gestión de los residuos/ There is a good waste management
-
2.24 Se realiza una almacenaje y señalización correcta de los residuos/ There is a proper storage and signaling of the waste area
-
2.25 El equipo de trabajos disponen de medios de recogida o contención de los residuos/ The work equipment has the equipment and the resources to contain the spills and waste
-
2.26 Existe una adecuada organización de los trabajos/ There is a good planning and organization of the tasks
-
2.27 Se realizan inspecciones o controles de seguridad, antes durante y después de los trabajos/ The check and safety inspections are implemented on site (previous, during , and after the works)
-
2.28 Se dispone y hace uso de la documentación de seguridad necesaria para la realización de los trabajos/ The work equipment has the safety documentation available to carry out the different tasks
-
2.29 Se están realizando los trabajos bajo condiciones climatológicas adecaudas/ The weather conditions are suitable to develop the different activities
B) Activities with special Risk
3.0 TRABAJOS ESPECIAL PELIGROSIDAD/ Task with special Risk.
-
Any activity with special risk is carrying out?
-
Que tipo de trabajos se están desarrollando?/ What type of activities do it carry out on site?
- IZADO DE CARGAS/Lifting Operations
- ESPACIOS CONFINADOS/Confined Space
- TRABAJOS EN CALIENTE/Hot Works
- TRABAJOS RIESGO ELÉCTRICO/Electrical Tasks
- TRABAJOS EN ALTURA/Work at Heights
3.1 IZADO DE CARGAS/ Lifting Operations
-
The absence of the Lifting plan (3.1.1), must be marked the option Class III as failed reponse
-
3.1.1 Se dispone y se ha informado del procedimiento/instrucción y del plan de izado/ The work team has avaialble on site , and have been informed about the protocol/instruction and lifting plan
-
3.1.2 Los equipos y maquinaria de izado son correctos y están en buen estado para realizar la maniobra/ The lifting equipment and machinery are in a good conditions, and are the suitable to carry out the lifting
-
3.1.3 Existen una organización adecuada para realizar la maniobra / There is a good organization to carry out the lifting
3.2 TRABAJO EN CALIENTE/ Hot Works
-
If The work are have been not protected and signed (3.2.2), must be marked the option Class III as failed response
-
3.2.1Existe una planificación de los trabajos/ There is a proper planning of the tasks
-
3.2.2 La zona de trabajos esta preparada, protegida y señalizada/ The work area have been prepared, singed and protected
-
3.2.3 Los equipos de emergencia se encuentran disponibles en la zona de trabajo/ The emergency equipments are available on the work area
-
3.2.4 Se dispone y se hace un uso correcto de los equipos de protección contra riesgos térmicos/the workers have and are using the specific ppe´s against the thermal contact risk
3.3 TRABAJOS RIESGO ELÉCTRICO/Electrical works
-
Will be failed response if have been not implemented the 5 golden rules (electrical task) (3.3.3)
-
3.3.1 Se dispone del procedimiento, instrucción y las habilitaciones necesarias para realizar trabajos de riesgo eléctrico/ The work team has the protocol, instruction and the electical competence required to carry out the electrical works
-
3.3.2 Se disponen y hace uso de los equipos de bloqueo y señalización/ the work team has been implemented the "LOTO" safety practices
-
3.3.3 Se han cumplido las 5 reglas de oro/ The five golden rules have been implemented
-
3.3.4 Los equipos de medida y de protección son acordes al tipo y potencia de la instalación/ The measures and protection equipment are suitable to the voltage of the electrical installation
3.4 TRABAJOS EN ALTURA/ Work at heights
-
The absence of the rescue and evacutaion equipment (3.4.3), must be marked the option Class III as failed reponse
-
3.4.1 Se está utilizando equipos de protección contra caída de altura, correctos al tipo de trabajo/ The workers are using the work at height ppe´s properly
-
3.4.2 Los puntos de anclaje, línea de vida, etc. están en buen estado de revisión/ The anchorage point, safety line, etc. are in a good conditions and checked.
-
3.4.3 Se dispone de un equipo de rescate y evacuación, y los trabajadores conocen su uso/There is a rescue and evacuation equipment. The workers knows the use of these equipments
3.5 ESPACIOS CONFINADOS/ Confined Space
-
The absence of the rescue system (3.5.3), must be marked the option Class III as failed reponse
-
3.5.1 Se ha establecido un protocolo o procedimiento de acceso y evacuación/ An access and evacuation protocol is implemented on site
-
3.5.2 Se dispone de permisos de trabajo/ It is available and implemented a work permit system
-
3.5.3 Se disponen de los equipos de rescate y evacuación adecuados/ It is available the rescue and evacuation equipments on site
-
3.5.4 Se han informado y formado a los trabajadores sobre el protocolo de acceso y evacuación/ The work team have been informed and trained of the access and evacuation protocol
C) Summary and Signature
-
Other Comments
-
Site Manager/ Supervisor
-
Auditor