Pre-construction Information Audit
General Arrangements
-
Notifiable definition - last longer than 30 working days and have more than 20 workers working at the same time at any one point or will exceed 500 person days
-
Is the project notifiable
-
Has an online F10 notification form been submitted to HSE to notify them of commencement of work
-
Explain why this has not been submitted
-
Have you checked that the principal designer (PD) has the capability and necessary skills, knowledge, training and experience to fulfil their duties under CDM
-
Have you checked that the principal contractor (PC) has the capability and necessary skills, knowledge, training and experience to fulfil their duties under CDM
-
Has the Department Head made formal appointments by letter to the PD & PC
-
Why not
-
Attach letters
Project Description
-
Is there a “client brief” including a description of the project, reasons for the work and design vision
-
Are drawings available
-
Do the PC/ PD have Client details including key contacts
-
Has a schedule of the key activities for the project been produced
-
Do the PC/ PD know the expected start and finish dates and any other milestone dates
-
Do the PC/ PD know programme details
-
Have Alpheus allowed time for work planning after the appointment of key contractors
-
Have Alpheus allowed adequate resources and time to each stage of the project
-
Has Alpheus provided details of existing records and plans to the PD/ PC
Client’s Considerations and Management Requirements
-
Has a construction phase plan (CPP) been adequately developed by the PC and reviewed by Department Head or delegate
-
Explain why
-
Have arrangements been made for communication and liaison between the parties involved, e.g. regular meetings
-
Are security provisions and requirements, e.g. access control, clear to the PD/ PC
-
Are you satisfied that suitable welfare & first aid facilities have been made available for use by contractors on site
-
Are any facilities and equipment which are to be made available, such as anchor points and lifting equipment suitable
-
Are the Supervision levels to be provided on site by the PD/ PC adequate
-
Have Alpheus provided any rules regarding parking, traffic routes, vehicle movement restrictions to the PD/ PC
-
Have permit-to-work arrangements been agreed with the PD/ PD
-
Have site fire safety requirements and emergency procedures been agreed with the PD/ PC
-
Have any restrictions concerning access, storage, waste and deliveries been discussed with the PD/ PC
-
Have any smoking restrictions on site been discussed with the PD/ PC
-
Have any height or weight restrictions on site been discussed with the PD/ PC
Hazards
-
Have details of existing “confined spaces” on the site been discussed with the PD/ PC
-
Have details about the location of asbestos-containing materials on site been discussed with the PD/ PC
-
Have any other hazardous materials on site been discussed with the PD/ PC
-
Have any adjacent land uses, where applicable, been discussed with the PD/ PC
-
Have any hazardous or dangerous materials stored on site been discussed with the PD/ PC
-
Have location of existing services including overhead lines and buried services been discussed with the PD/ PC
-
Has information about ground conditions where this is relevant to the job (e.g. excavation) or the safe use of plant been discussed with the PD/ PC
-
Have details about existing structures to the extent that it is relevant to the work? (including relevant information from any existing health and safety file) been discussed with the PD/ PC
-
Has information about past incidents and ground movements which may have affected the stability of structures been discussed with the PD/ PC
-
Have details of any contaminated land been discussed with the PD/ PC
-
Have any other health or safety hazards arising from the client’s (our) activities been discussed with the PD/ PC
Design Issues
-
Have any significant design assumptions been discussed with the PD/ PC
-
Have suggested work methods, sequences or control measures put forward by those acting as designers been discussed with the PC
-
Have arrangements for co-ordination of ongoing design work and handling design changes been discussed with the PD/ PC
-
Has significant residual risks identified at the design stage but which could not be eliminated been discussed with the PC
-
Have materials requiring particular precautions in their use been discussed with the PD/ PC
The Health and Safety File - projects involving more than one contractor only
-
Has the format for the health and safety file and its content been agreed with the PD/ PC
Comments
-
Any further comments
Sign Off
-
Completed by