Title Page
Project Details:
-
Client:
-
Project:
- REA’s RURAL ELECTRIFICATION EXPANSION PROGRAM PHASE III ROUND II
-
Contract Number:
Inspection Details:
-
Inspection Reference:
-
Date/Time:
-
Subject:
- INSPECTION REPORT for Energizing OH MV/LV Line (IR)
-
Project Title:
- REEP Phase III Round II MAI – TANESCO – REA - JV Guangdong Jianneng Electric Power Engineering Co. LTD AND White city International Contractors LTD
- REEP Phase III Round II MAI – TANESCO – REA - NAKUROI Investment Co.ltd
Venue:
-
Region:
-
District:
-
Location:
-
SUBSTATION NO. [Transformer (Tx) Plate]:
ATTENDEES / PARTICIPANTS:
-
For REA Representative:
-
For TANESCO Represntative:
-
For Consultant representative:
-
For Contractor Representative:
ABSENTEES / DISTRIBUTION:
-
For REA Representative:
-
For TANESCO Represntative:
-
For Consultant representative:
-
For Contractor Representative:
-
FILE DISTRIBUTION:
NOTE:
-
If within 48 hours from this document submission, no official objection by participants are given, it will be considered that there are no any objections and that each participant accepted his tasks, duties, responsibilities and deadlines herewith given.
Endorsed by MAI Consult:
-
Name: Eng. Kassim Ismail Ngoroka
-
Position: Supervisor
-
Date of Issue:
FINDINGS AND RECOMMENDATIONS
The following were the findings and recommendations after the inspection:
-
This is a MV/LV NEW village.
-
All Customers within the scope have to be connected with cables and meters.
-
The site is yet to be energized.
-
Total ACSR 100mm sq, DOG (km) :
-
Total ACSR 50mm sq, RABBIT (km) :
-
Total MV line length (km):
-
Total LV Single Phase lines length (km):
-
Total LV Three Phase lines length (km):
-
Total LV line length (km):
-
Total distribution transformers (Nº):
-
Total single-phase customers (Nº) :
-
Total three-phase customers (Nº) :
A. OH LV LINE 240V or 415V
1. LV Survey:
-
Has the site been surveyed and pegged?
-
Has the site been checked against drawing?
-
Have all relevant acts, laws, standards and instructions been complied with?
2. LV Bush Clearing
-
Bush Clearing
3. LV Pole Installation & Condition:
-
Depth of pole holes. As per designed standard and Drawing Approval of TANESCO
-
Pole alignment. As per design Approval
-
Back filling of pole done Properly
-
Line Alignment, As per design Approval?
-
No Any Pole had been damaged?
-
No any Pole had cracks – split?
-
Has the Pole had a manufacturer name plate?
-
No Any Line Interference with HT?
-
Adherence to pole schedule?
4. Pole Dressing.
-
Pole caps on top of Pole (if wooden Pole )
-
Nuts C/W washers. As per Drawing Approval.
-
Size of Bolt as per standard and design?
-
Danger/Hatari Plate installed?
-
LV line Sections ok?
5. LV Cable Stringing
-
Span Length As per TANESCO Ground Clearance and Approval Design.
-
Tensioning and sagging as standard?
-
Clearance Between Cable & Ground as per standard?
-
Ground clearance Ok?
-
Jumpers neat and done properly as per standard?
-
Cables suspension clamp on pole.
-
Cable stringing Ok?
-
Service cable accessories as per standard
-
Proper Tension/Strain Clamps Used in sections?
-
All Cable Terminals are properly Terminated and sealed with Cable Endcaps?
-
Are All Angled structures treated as per Standard and design?.
6. Stays (Normal, Flying, Outrigger, Guy)
-
Support Angle (at Pole) as per standard?
-
Distance of stay hole from pole as per standard?
-
Support point in relation to load on pole (Closest possible point to the Loaded Point)
-
Alignment between stay and pole Ok?
-
No Missing stays?.
-
No Loose stay?
-
No Loose hanging gay grips (teils)?
-
Stay Hole Depth ( Shoe Shape ) as per TANESCO Approved standard.
-
Size of stay wire & Rod/pole used as per standard?
-
Vertical Distance of stay insulator from Ground level >3 met?.
-
Stay make off ok?
-
All Stays are well dressed, buried and tail bound as per requirement?
7. Meter Connection
-
Meter Positioning ok?
-
Securing of Meter Ok?
-
Distance between Customer & pole. As per the TANESCO Standard?
-
Meter Gland for Service Cable for single or 3 phase connections?
-
ABC tension clamp for Service cable on both sides?
-
Service cable accessories as per TANESCO Standard?
-
Termination of Service cable at Customer point. As per TANESCO Standard?
-
Recommendations:
B. OH MV LINE 33 KV
1. HT Survey
-
Has the site been surveyed and pegged?
-
Has the site been checked against Contract?
-
Have all relevant acts, laws, standards and instructions been complied with?
2. HT Bush Clearing
-
5 met clearance on either side of Line for 33 KV as per TANESCO standard.
3. MV Pole Installation & Condition
-
Pole Depth properly done.
-
Standard poles installed as per design and standard Requirements?
-
Pole Alignment OK?
-
Line Alignment, As per design Approval?
-
Back filling done Properly, As per design Approval?
-
No Any Pole has been damaged?
-
No Any Pole had cracks – split?
4. MV Pole Dressing
-
Pole caps on top of Pole ( If Wooden Pole )
-
Nuts Complete with Washers, As per Approved Drawing.
-
Anti -Climbing device/barbed Wire installed?
-
Danger/Hatari Plate installed in proper position?
-
All Pole Number plates Installed and proper position?
-
Pole manufacture plate height Ok?
-
Span Length As per TANESCO Ground Clearance and Approval Design.
-
Adherence to pole Schedule
5. MV Conductor Stringing
-
Tension and Sagging. No Wave
-
No Conductor kinks ,loose slice or broken?
-
Mid-Span Joints quality (Neat Joint)
-
T-Off Connection (Neat U loop for 33 KV)?
-
Ground Clearance As per TANESCO Standard
-
Conductor Spacing As per TANESCO Standard
-
Jumper and Termination (Neat with PG Clamp)
-
Line Separation As per TANESCO Standard
-
Are All Angled structures treated as per Standard and design?.
6. MV Insulator Installation
-
Conductor Binding on Insulator & Insulator Clamps Tightened?.
-
Conductor Termination to dead end Clamps?.
-
Insulators properly installed?.
7. Stays (Normal, Flying, Outrigger, Guy)
-
Support Angle (at pole ) as per standard?
-
Distance of stay hole from pole as per standard?
-
Support point in relation to load on pole (Closest possible point to the Loaded Point)
-
Stay Hole Depth ( Shoe Shape ) as per TANESCO Approved standard.
-
Anti -Climbing Barbed wire ( 3 Meter from ground)
-
Size of Stay Wire and Rod/Pole used, As per TANESCO Standard
-
Vertical Distance of stay insulator from Ground level 3 met.
-
All Stays are well dressed, buried and tail bound as per requirement?
8. Continuous Aerial Earth
-
Every 5th Pole Grounded within 2 km from each side of Transformer.
-
Each terminal pole grounded.
-
Shield Wire properly installed.
-
Recommendations:
Three (3) phase TRANSFORMER 50KVA, (33/0.4/0.23 KV)
-
Transformer Manufacturer Serial Number:
1. Installation or Mounting
-
Transformer (TF) Mounting done Properly?
-
Transformer Anchorage. Tied and Welded
Transformer condition
-
No Damaged on Fins or Bushing During Transport.
-
No Damaged During Installation.
-
No leakages.
-
Transformer oil level as per standard.
-
All Arching Horns are well aligned?
2. Transformer Dressing
-
MV Loop (U-Loop)
-
MV Droppers (Neat With Pilot insulator)
-
Channels (Leveled and Firmly Fixed)
-
MV Fuses (Neat and as Per rating Designed)
-
LV Fuses (Neat and as Per rating Designed and with covers)
-
LV Wiring (Neat)
-
Ground Clearance, As per Approved Drawing.
-
S/S Numbering & Hatari as per Approved Drawing.
-
Surge Diverters installed &at the correct position, As per Approved Drawing.
-
Spark properly aligned.
-
Security light (water-resistant) with 50W bulb fitted.
3. Earthing
-
MV Earthing (≤ 10 Ohm)?
-
LV Earthing ( ≤ 2.5 Ohm)?
-
Surge Divertor Earthing ( ≤ 10 Ohm?)
-
MV, TF Earthing (All Separate Earthing)
-
Recommendations
INSPECTION CONCLUSION
REMARKS FROM TEAM
-
General Remarks from the Inspection Team
-
Contractor's Commitment on Pending Issues
-
Energization Approval
- APROVAL granted to energize MV & LV Network
- APROVAL granted to energize Only MV Network & Substation
- NO APROVAL granted to Energize the MV/LV Network until Major Snags are cleared
INSPECTION TEAM
-
FOR CONTRACTOR REPRESENTATIVE (Site Manager/Engineer)
-
FOR CONTRACTOR REPRESENTATIVE (Site Supervisor)
-
FOR CONTRACTOR REPRESENTATIVE (Site Foreman/Lineman)
-
FOR CONSULTANT REPRESENTATIVE (Supervisor Engineer)
-
FOR CONSULTANT REPRESENTATIVE (Assistant Supervisor)
-
FOR TANESCO REPRESENTATIVE (Project Engineer)
-
FOR TANESCO REPRESENTATIVE (District Representative).
-
FOR REA REPRESENTATIVE (Project Engineer)
-
FOR REA REPRESENTATIVE (Project Coordinator)