Title Page

  • Project Number

  • Date

  • Project Name

  • Discipline

  • Drawing Number

  • Revision

  • Prepared by

  • Location/ Building
  • Level/Floor

  • Area

undefined

  • 1 Check with the specification/drawing that the equipment is the correct type, size and in the right location, correctly supported and fixed with required access.

  • 2 Check for external and internal damage, rust, chipped paint, dents and visible signs of damage and deterioration.

  • 3 Check internal heating/cooling battery fins.

  • 4 Check AHU doors are locked (P&RM to retain keys until handover).

  • 5 Check that pipes are correctly aligned and have flexible connections if specified.

  • 6 Check control valves fitted are in accordance with controls schematic.

  • 7 Check units can be isolated and drained.

  • 8 Check all brackets are plumb and tight.

  • 9 Check that flanges and unions are installed in the correct position to allow heater batteries to be withdrawn.

  • 10 If cooling battery fitted, ensure condensate pipework is correctly installed, complete with adequately sized water seal and run to an appropriate drain point, floor gully.

Remarks

  • undefined

Sign Off

  • Name and Signature

  • Name and Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.