1 Check with the specification/drawing that the equipment is the correct type, size and in the right location, correctly supported and fixed with required access.
-
2 Check for external and internal damage, rust, chipped paint, dents and visible signs of damage and deterioration.
-
3 Check internal heating/cooling battery fins.
-
4 Check AHU doors are locked (P&RM to retain keys until handover).
-
5 Check that pipes are correctly aligned and have flexible connections if specified.
-
6 Check control valves fitted are in accordance with controls schematic.
-
7 Check units can be isolated and drained.
-
8 Check all brackets are plumb and tight.
-
9 Check that flanges and unions are installed in the correct position to allow heater batteries to be withdrawn.
-
10 If cooling battery fitted, ensure condensate pipework is correctly installed, complete with adequately sized water seal and run to an appropriate drain point, floor gully.