Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1.0 - Installation (INT)
-
INT-1 - Standards
-
Installation has been delivered as per AV Standards and Best Practices
-
Include Photos of Installation:
-
Notes:
-
INT-2 - Cable Continuity Testing
-
All Cables have been tested, labelled and tests recorded on the Cable Continuity Test Plan
-
Notes:
-
INT-3 - Design Deviation
-
In the case of Design Deviation, a complete set of digital markups with details of deviation has been provided.
-
Notes:
-
INT-4 - Safety
-
All Installation safety measures have been implemented as defined by Vendor and AV Best Practice
-
Notes:
-
INT-5 - Video and Audio Testing
-
Video and Audio tests have been completed to verify that solution is ready for Commissioning
-
Notes:
2.0 - Documentation (DC)
-
DC-1 - Inventory Log
-
A full inventory log has been provided including all serial numbers, MAC addresses, software releases and IP addresses. Devices marked as Installed/Non Installed. Non installed devices include reason why
-
Notes:
-
DC-2 - CAD Markups
-
A complete set of digital markups has been provided.
-
Notes:
-
DC-3 - Cable Continuity test plans
-
Completed Cable Continuity test plans has been provided
-
Notes:
3.0 - Software (SW)
-
SW - 1 - Programming Testing
-
Custom Software has been tested to confirm that solution is ready for Commissioning
-
Notes:
-
SW – 2 - Custom Software files
-
All Custom software files has been provided.
-
Notes:
4.0 - Inventory (IVNT)
-
IVNT -1 - Non-Installed Items
-
All Non-Installed Items returned to warehouse
-
Notes:
5.0 - Site Conditions (SITE)
-
SITE – 1 - Equipment
-
All Equipment removed from Site
-
Notes:
-
SITE – 2 - Cleanliness
-
Site has been left clean and all garbage has been removed
-
Include Photos of Site Conditions:
-
Notes: