Final Inspection Checklist for J2 & L14 Wheel Motors

  • Verify the test run checklist is in the pouch and signed off.

  • Vibration data: Confirm that vibration data has been reviewed & approved.

  • Check to see that a final commutator profile (TIR) has been accomplished.

  • Shell Pinion: Is it seated against the labyrinth seal?

  • Brake Hub: Is it seated against the labyrinth seal?

  • Is brake disc secured with 12 each grade 8 bolts (P/N R0021630)?

  • Has rotor been locked?

  • Are leads secure for shipment?

  • Has motor been blown out and all debris cleared?

  • Is work-scope checklist signed off?

  • Verify that the Job Acknowledgement information matches the nameplates.

  • Make sure pictures are taken before motor is wrapped in plastic.

  • Is parts list in the job pouch from warehouse/receiving area?

  • Are all bolted connections tight?

  • Is prep & paint up to Mesa Joy Global quality standards?

  • Have job number and country of origin been stamped in unit?

  • Ensure job number, serial number, part number, and completion date is written on outside after motor is wrapped.

  • Megger and record the following readings: Armature circuit: Shunt field: Between circuit:

  • Ensure there are four (4) desiccant crystal packets added to the outside of a motor prior to wrapping the motor in plastic. (ALL MOTORS)

  • Inspector's name:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.