Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Reception
-
Are both sliding doors in good working order and clean?
-
Are all areas of reception vacuumed and clean for visitors on arrival?
-
Is correct signage on display for current changes or out of orders?
Plantroom
-
Is the plant room door locked?
-
Are the PPE lockers accessible?
-
Are the pool water readings within set parameters as defined on the pool test sheet?
-
Are ladders secure to wall with chain and padlock?
Pool hall
-
Are the Torpedo boys in place and in working order?
-
Is the spinal board in place?
-
Are the first aid boxes and face masks in place?<br>
-
Are both caps on the pool vacuum outlets in place and secured?<br>
-
Is the poolside safety signage in place and visible?
-
Is the lifeguard chair safe to use and in the correct position?
-
Are all pool ladders safe for use?
-
Has the flume and child slide been checked?
-
Has the seating area and spectators seating been swept and clean?
Changing village wet side and toilets.
-
Ensure all baby changers are clean and in full usable order.
-
Are showers, sinks and toilets in full working order?
-
Flush main Wet side changing room showers for 30 seconds
-
Flush female wet side showers for 30 seconds
-
Flush male wet side showers for 30 seconds
-
Flush disabled shower for 30 seconds
-
Are all changing rooms, lockers, walkways and gullies clean - AM
-
Is the disabled changing hoist, chair,bed present and in full working order?
Gym
-
Is the music system turned on in the power plates room?
-
Is all of the Gym equipment turned on - AM<br>
-
Is all of the Gym equipment turned off - PM<br>
Kitchen
-
Have the fridge checks been completed?
-
Has the kitchen been left in a clean and tidy condition? - AM
-
Has all kitchen equipment been turned off? - PM
-
Is the internal kitchen door between LK and catering locked - PM
-
Ensure hot water on chocolate machine is switched off - PM
Thursday facility checks.
-
Reacom and Disabled Alarm Switches to be Tested. <br>Are all switches and Main Box in Good Working Order?<br>
Plant Room Checks - Scroll to page 3
General Operations
-
Have the back gates been unlocked?
-
Check all lighting and emergency lighting
-
Change backup disc.
-
Is the AED in place?
-
Visual check OK?
- yes
- no
-
Are the fire doors, exits and routes free from obstructions and clear, check sheet completed
-
Are all fire extinguishers in the correct location.
-
Are wheelie bins away from building and secured with the wheel stoppers on? AM
-
Does the lifeguard and the Manager on Duty have a working radio
-
Has the Manager on Duty mobile been fully charged?
-
Has reception been opened and Ezrunner switched on
-
Has the fire alarm panel been checked and is fully operational? (Report any faults)
-
Has the raecom panel been checked and free from faults?
-
Are all areas clean and ready to open the centre?
-
Is the evacuation box in place?
-
Is all safety posters and signage in place and is visible?
-
Check disabled toilet and changing rooms alarms are operational.
-
Has the lift alarm been tested?
-
Ensure all evacuation cards are in place.
-
Check customer comment box and action if needed.
-
Has a safe check been completed? - AM
-
Are staffing levels correct? - AM
-
Do all staff comply with company uniform regulations and are they wearing a name badge? - AM
-
Has the A frames been placed outside on opening?
-
Complete external check of the building and pathways inc. bike rack
-
Are wheelie bins away from building and secure with wheel stoppers on? PM
-
Are staffing levels correct? - PM
-
Do all staff comply with company uniform regulations and are they wearing a name badge? - PM
-
Ensure cleaning cupboard tidy and locked - PM
-
Has a safe check been completed? -PM
-
Early MoD
-
Late MoD
Pool Test & Enviromental Control Log
Main Pool - Manuel Test.
-
Pre-opening
-
Are all pre opening levels within parameters?
-
If parameters are not met please enter information on action taken.
-
Mid-day Test
-
Are mid-day readings within parameters?
-
If parameters are not met please enter information on action taken.
-
Post Closing
-
Are post closing readings within parameters?
-
If parameters are not met please enter information on action taken.
Spa - Manuel Test.
-
Pre-Opening
-
Are pre opening readings within parameters?
-
If parameters are not met please enter information on action taken.
-
Mid-day Test
-
Are mid-day readings within set parameters?<br>
-
If parameters are not met please enter information on action taken.
-
Post Closing
-
Are post closing readings within set parameters?
-
If parameters are not met please enter information on action taken.
-
End of day image capture of pool test & environmental control log.
Plant Room Checks
Plant Room
-
Walking through looking down at pumps check for water.<br>Is the area clear of water and obstructions?<br>
-
Balance Tank - Check Level if having to top up then comment below
-
Comments
-
Are all boilers in working order and on?<br>
-
Check shower pressure are they within parameters on slider, indicate the level. <br>
-
Check temperature levels of showers?
-
Are all valves on yellow filters closed?
-
Are the filter pressures within parameters set on the dials?
-
Where shower rinse is next to filters, check levels of aluminium sulphate top up if needs.<br>If empty the ratio is quarter aluminium and then top up with water till top.<br>Wear appropriate PPE.
-
Make up board - is it on or off?
-
Sauna and spa panel are they within set parameters for daily use?