ITP#1012 Underground Conduit Installation
-
Theiss MBR
-
Project # 2712
-
Station designation
-
ITP Number
THEISS MBR ITP#1013 UNDERGROUND CONDUIT
-
STATION & LOCATION ie- Murrumba Downs Station
-
INSPECTION / TEST POINT Check for latest drawings and co-ordinates
-
Compliance Criteria - Drawings Civil and electrical
-
Hold point- No
-
Method of inspection- Visual, Administrate
-
Person Responsible- Supervisor
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Excavate to required depth in accordance with relevant trench cross section
-
Compliance Criteria- Drawings, trench cross section, HV longituditional section, Datum point
-
Hold point- No
-
Method of inspection- Visual, measurement
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Install conduits- level
-
Compliance Criteria- Drawings, electrical specification
-
Hold point- Yes
-
Method of inspection- Visual, photographic
-
Insert photos as required
Photo
-
Trench photo
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Back fill trench-300mm layer
-
Compliance Criteria- Electrical specification- stabilised sand if required
-
Hold point- No
-
Method of inspection- Visual, measurement
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Compact trench
-
Compliance Criteria- Electrical specification
-
Hold point- No
-
Method of inspection- Visual,
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Install electrical or communications tape at correct level
-
Compliance Criteria- Electrical specification, AS/NZ 3000
-
Hold point- No
-
Method of inspection- Visual,
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Back fill trench-300mm layer
-
Compliance Criteria- Electrical specification- stabilised sand if required
-
Hold point- No
-
Method of inspection- Visual, measurement
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Compact trench
-
Compliance Criteria- Electrical specification
-
Hold point- No
-
Method of inspection- Visual,
-
Person Responsible- Leading Hand
-
Add signature
-
Comment
-
INSPECTION / TEST POINT Submit to Klenner Project Manager, including mark up of relevant area and photos.
-
Compliance Criteria- Electrical specification
-
Hold point- No
-
Method of inspection- Visual,
-
Person Responsible- Supervisor
-
Add signature
-
Comment