Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Location
-
Add location
-
Elevation
-
Gridline Refrence
-
Level
- Ground
- First
- Second
- Third
- Fourth
- Fifth
- Sixth
- Seventh
- Eight
Stage 1 - Structural integrity
-
Have pull test been undertaken in this area - 10% of all new / renewed fixings
- Yes
- No
- N/A
-
Has torque testing been undertaken - all new and renewed fixings
Stage 2 - Remediation of shims & brackets
-
Have all plastic shims been removed and replaced with metal, new brackets introduced where shims exceed 25mm, all box section packers removed and replaced with metal shims
-
Have new intermediate rails been installed in correct position with the correct fixing type as per the construction issue drawings and structural details
-
Have the remedials to the concrete substrate been made good
Stage 3 - Cladding Panel, Coping, Brise Soleil
-
Has making good to existing cladding panel finished been undertaken using the correct material and warranted for 15 years minimum
- Yes
- No
- N/A
-
Has the cladding panels been installed at the correct position and free from defects or scratches
-
Has the coping panels been secured as per the correct detail
-
Has the Brise Soleil been been recoated, reinstalled, and defect free
Stage 4 - Handover
-
Has this area been snagged by both LS and Clevetts and all items raised closed down
-
Sectional completion issued
-
Sectional completion certificate
-
Signed for on behalf of Lancer Scott
Photo Evidence
-
Photos