Title Page
-
Project Code and Name
-
Contractor on site
-
Contractors Representative on site
-
Conducted on
-
Audit completed by
-
Location of project works
-
Description of works on site
Site House Keeping
-
Does the site appear tidy and organised?
-
Take a picture of the construction area
-
Are there spill kits on site?
-
Have staff on site been through spill response training?
Construction Environmental Management Plan
-
Is there an approved CEMP on site?
-
Have all staff on site been briefed on the CEMP?
-
Have the relevant pre-construction briefings been completed?
-
Are all the required site inspections and routine checks being completed as detailed in the CEMP?
Dust
-
Are the dust control measures identified in the CEMP implemented?
Contaminated Land
-
Has the Contaminated Land Site briefing been completed?
-
Is the Contaminated Soil Management Plan implemented on site?
-
Are soil disposal logs recorded?
Archaeology
-
Has the Archaeologist site breifing been completed?
-
Are the Archaeology control measures in the CEMP implemented?
Erosion & sediment control
-
Are the erosion & sediment control measures identified in the CEMP implemented on site?
Noise
-
Are the noise measures in the CEMP implemented on site?
Hazardous Substances
-
Are there any hazardous substances stored on site?
-
If so are they stored in accordance with procedures set out in the CEMP?
Other Environmental Effects, issues including any positive site observations
-
Please note down any other environmental management procedures implemented on site.
-
Take photo if required
-
Please provide an audit summary and any relevant site information
-
Take photo if required