  • Project

  • Council / MW Representative

  • Council
  • Conducted on

  • Prepared by

  • Document No.

  • Verify MAIN DRAIN personnel (pipe layer and site supervisor) are current<br>

  • Qualification of operators current<br>

  • Trench Safety Awareness Supervisor nominated<br>

  • NAME:

  • Worksafe has been notified of the works <br>

  • Traffic control requirements identified<br>

  • Control and protection of public identified<br>

  • Storage area of materials and equipment identified<br>

  • Three (3) temporary bench marks identified<br>

  • Setout survey completed<br>

  • Road opening permits secured<br>

  • Current construction drawings and specification on hand<br>

  • REVISION:

  • Services and obstructions identified / Authorities advised<br>

  • MOCS:

  • Confirm existing connection levels prior to commencement of pipe laying.<br>

  • Contractor to cater for surveyors (Refer NOTE)<br>

  • Reinforce MAIN DRAIN access/connection requirements (Refer NOTE)<br>

  • Detailed report/photos taken of adjoining properties<br>

  • Site Management Plan – reference to JSA, SWMS, Toolbox<br>

  • Confined Space Entry form to be completed and forwarded to Consultant and relevant Authority
    Connection to Melb. Water assets request to be forwarded to Consultant and relevant Authority
    Contractor to advise Consultant five (5) clear days prior to requirement for inspection of assets
    Inspection of Assets request to be forwarded to Consultant and relevant Authority
    Contractor to advise Consultant five (5) clear days prior to requirement for surveyors
    Contractor to advise Consultant five (5) clear days prior to undertaking works within road reservation incl. copy of approved TMP
    Contractor to advise Consultant five (5) clear days prior to undertaking works within private land
    Variations MUST be reported to the Superintendent before proceeding further otherwise at Contractor risk of NCR and costs.
    ANY deviation from approved plans must be informed to Superintendent prior otherwise at Contractor risk of NCR and costs.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.