Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Project Tracking SCC
Post Award initial activities
-
Have C&D Specifications 1742 been reviews and has C&D Waste Management plan been uploaded to cdwaster@wal-mart.com
-
Has Spec section 1640 been reviewed and printed and a Furnished By Owner Tracking Log been established?<br>
-
Has an email been sent to Wal-Mart purchasing to procure the "X" list of Owner Provided Vendor contacts don.callaway@ wal-mart.com<br>
-
Has group email been sent to all Walmart vendors requesting release forms?<br>
-
Site trailer, fencing, toilets ordered?
Owner Expectations- First 14 days
-
Approved permits been paid for and present in the job trailer?
-
BMPs installed, binders built and online documents match hard binder?<br>
-
Have you scheduled your SWPPP Certification Meeting ( if Applicable )
-
Site trailer in place with temp power, phone and internet?
-
Temp utilities transferred to Shames
-
Is your controlled access and badging system in place?
-
Has your fencing been installed and your lay down yard established?<br>
-
Have utility Company's all been contacted to confirm owner contracts are signed and pre construction meetings being scheduled to discuss required install dates?
-
Is the Wal-mart required contact list on site?
-
Has the Construction Schedule been posted on the trailer wall?
-
Has all required job-site signage been installed?
-
Have the compliance wall of documentation been set up and all required paperwork and binders in place?
-
Are project plans noted, stamped for Construction on site?<br>
Required trailer and site documentation
-
Baseline Schedule?
-
Three week look ahead schedule?
-
Project Specifications?<br>
-
Deviation and RFI Log?<br>
-
Construction Manager reports?<br>
-
PCR/CO Log?<br>
-
GC Checklist?<br>
-
Vendor 1640 Spec and tracking log?