Information
-
Job Number
-
Client / Site
-
Conducted on
-
Prepared by
-
Personnel
This procedure applies when changing over existing or installing a new switchboard
Do you have all PPE required?
-
Steel capped boots
-
Hi-vis clothing
-
Safety glasses (when required)
Hazards
-
Electric shock
Control Measures
-
Isolate and test
Procedure
-
1. Isolate
2. Mark all cables
3. Disconnect
4. Remove old switchboard
5. Install new switchboard
6. Connect
7. Test
8. De-Isolate
9. Test polarity & RCD's
Notes
-
Notes or other hazards identified:
-
Photos if needed
-
I have reviewed this Standard Operating Procedure and agree with the hazards identified and agree to adhere to the procedure
-
Name of signee(s)