Title Page
-
Conducted on
-
Prepared by
Project Details
-
Project Name
-
Client
-
Project Location
-
Responsible Supervisor
Recommendation
Recommendation
Work at Height
-
Is there a safe method of getting to and from work area?
-
Have personal fall arrest system been provided for all workers where necessary?
-
Are safety harnesses worn by all persons working at height and they are securely fixed to a foxed point at all times to stop their fall?
-
Are shock absorbing lanyards used in all cases?
-
Does fall protection equipment in good condition and do not show any damage? This confirmed by site in-charged?
-
Does hand tools used while working at height tethered and protected from falling?
Mast Climber
-
Daily / pre-use inspection and weekly inspection carried out by personnel inducted by Brogan/IFAP demonstrator and inspection carried out and recorded before machine is put into use each day?
-
Access / egress to the structure / work area is sufficient and safe?
-
Exclusion zone perimeter fencing & signages is in place?
-
Check base ground area is suitable?
-
Working area / machine pathway is clear from debris and obstruction?
-
Check horizontal / vertical position of the platform
-
Mast section position vertically alligned?
-
Electrical cable is untangled, in good condition, secured to underside of platform and free hanging?
-
Fixings, hand rails, gates and guard of platform sections are in position?
-
Mast guards are in place?
-
Check function of the emergency stop on MCWP working?
-
Wall anchoring, bolts and connections installed?
-
Check for cement / mortar deposits that could impede the platform function.
Housekeeping
-
General neatness of working areas and good housekeeping maintained?
-
Walkways and working area to be clear, tidy, and free of debris & tripping hazards?
-
Maintain storage clean & materials properly stacked?
Personal Protection Equipment
-
Does the user wearing adequate / necessary PPE for the task?
-
PPE (helmet, safety shoes, jacket, gloves, safety glass) available and utilized in the project?
Documentation
-
Is Method Statement and Risk Assessment available and briefed to all MCWP personnel?
-
Is Toolbox talks meeting conducted in the project?
-
Is full body harness inspection being conducted and result is recorded on weekly basis?