1. Reinstatement
-
Is the temporary reinstatement free from trip hazards and left in a satisfactory manner?
-
Has all task related waste been removed from site?
-
Have grassed areas been top soiled and seeded and are free of debris?
-
Have garden beds been reinstated satisfactorily. Plants replaced, mulch and toppings free from clay or other materials?
-
Does permanent reinstatement and compaction meet Vic roads, Local Council, property owner’s requirements?
-
Have concrete saw over cuts been kept to a minimum?
-
Have concrete saw over cuts been removed as part of the hard surface reinstatement?
-
Where site is to be left overnight, are adequate protection measures, lighting and night guidance provided?
-
Has Refix / Relight been completed?
-
If required, was a red card left with correct information and details?
-
Has a clean up notice been left with the consumer?
2. MG Standards
-
Have MG standards (meter locations, clearances, etc.) been maintained?
-
Does pipe coating meet MG standards?
-
Does construction meet MG requirements?
-
Have other authority’s assets been identified and proved?
-
If required, has meter protection been installed?
-
Has fitting line been installed in accordance with AS 5601?
-
Has regulator vent been installed and installed correctly?
-
Has slab and enclosure been installed?
-
Does the slab and enclosure meet MG standards?
-
Is tracer wire in place at up stands?
-
Is Manifold/Up stand supported as per MG requirements?
-
Have all marker posts been installed as per MG requirements?
-
Have valve syphon test point etc covers been installed as per MG requirements?
-
Is there evidence of a satisfactory area covered for leakage location and identification?
-
Has a line valve been installed as per MG requirements?
-
Has the abandoned service up stand been removed/cut from above ground?
-
Is the daily location sheet accurate?
3. House Keepiing
-
Crushed rock laid level and compacted.
-
Evidence of subsidence in compound and entry and exits.
-
Evidence of debris/rubbish.
-
Interior of compound clear of fire hazards, tidy.
-
Exterior of compound clear of fire hazards, tidy?
-
Fire Protection e.g. Fire Extinguishers, etc. in place and in test date.
-
Security of compound fence, gates etc.
-
Paint work on buildings, posts and bollards etc.
-
Warning signs, Emergency Contact details legible in place and with current information?
-
PPE signs/notification?
-
Comments
-
Overall Audit Rating
- 1
- 1.5
- 2
- 2.5
- 3
- 3.5
- 4
- 4.5
- 5
- 5.5
- 6
- 6.5
- 7
- 7.5
- 8
- 8.5
- 9
- 9.5
- 10