1 EMERGENCY RESPONSE

  • 1.1 Current Emergency Evacuation Plan & Procedure displayed in appropriate positions around site

  • 1.2 Fire Extinguishers are marked correctly on evacuation plan

  • 1.3 Firefighting equipment in place and in good condition

  • 1.4 Fire extinguishers are correct type for the area

  • 1.5 Fire extinguisher signage is in place and correct

  • 1.6 Fire extinguishers are serviced every 12 months and fitted with anti-tamper tags

  • 1.7 1 metre clearance maintained around fire fighting equipment

  • 1.8 Access to fire fighting equipment is clear

  • 1.9 Fire Breaks in place and adequate

  • 1.10 Access to switchboards is clear and unobstructed

  • 1.11 Smoke alarms fitted in nominated locations

  • 1.12 Emergency assembly / muster area(s) sign posted

  • 1.13 Emergency assembly / muster area(s) have a clear path to them and are free of debris

  • 1.14 First Aid kits are available with correct signage displayed

  • 1.15 First Aid kits in good condition and fully stocked (contents list is located on inside of kit - check)

  • 1.16 Sign in sheets accurate

  • 1.17 Emergency 'exit' signs present and illuminates (above fire doors and directing exits)

  • 1.18 Exits and stairs clear and unobstructed

2 House Keeping

  • 2.1 Access / Egress to work sites

  • 2.2 Caps on star pickets & rebar

  • 2.3 Rubbish bins provided and used

  • 2.4 Materials neatly stacked

  • 2.5 Work platforms clear

  • 2.6 Adequate lighting - night work

  • 2.7 All hoses off ground

  • 2.8 Waste stored / removed correctly

  • 2.9 Recycling is occurring

  • 2.10 Do employees pick up stock / litter / spillages off floor & site area

3 Offices and Ablutions

  • 3.1 Crib room clean, tidy and hygienic

  • 3.2 Floors are clean, clear with a safe path of travel throughout area

  • 3.3 Floor coverings / surfaces in good condition

  • 3.4 Toilets clean and hygienic

  • 3.5 No evidence of sewage spills or overflows

  • 3.6 Barricading / signs in place where required

  • 3.7 Access and Egress; trip hazards, condition of flooring, anti-slip, handrails

  • 3.8 Emergency Evacuation Plan

  • 3.9 Air conditioning & Ventilation adequate

  • 3.10 Filing Cabinets / Shelving - not overloaded

  • 3.11 Leads, Lighting, Emergency Lighting

  • 3.12 Housekeeping, cleanliness, food / rubbish disposal, hygienic

  • 3.13 Individuals Work Stations

  • 3.14 Office equipment; Shredder protected, good height, ventilation, noise

  • 3.15 Equipment such as chairs, desks, computers, etc. are in good working condition

  • 3.16 Lights are working, covers in place where required and adequate for the job

  • 3.17 Electrically operated machines have current testing and tagging (includes kitchen appliances older than 12 months

  • 3.18 Power points and power leads are good condition (no leads across floors or on wet surfaces)

  • 3.19 MSDS available

4 Personal Protective Equipment (PPE)

  • 4.1 PPE available at the worksite

  • 4.2 All appropriate PPE being worn

5 Mechanical / Workshop

  • 5.1 9" grinders not in use

  • 5.2 Clips fitted to all hoses

  • 5.3 Correct discs used in grinders

  • 5.4 Ladders secured and tagged

  • 5.5 guards fitted to machinery/ tools

  • 5.6 All power tools fitted with dead man

  • 5.7 Portable electrical equipment Tagged and current

  • 5.8 Wheel chocks in use / available

  • 5.9 Hand held tools are in good condition and stored appropriately

  • 5.10 Are sufficient stocks of PPE kept?

  • 5.11 Manual handling aids available

  • 5.12 Gas bottles secured / protected from damage or falling over ( e.g strapped or chained to secured fixture)

  • 5.13 Ladders used are in good working condition

  • 5.14 Safety warning signs present:

  • * Manual Handling

  • * Eye protection

  • * Keep out - Authorized Personnel only

  • * Visitors report to the Office

  • * Chemicals

  • 5.15 Employees are wearing correct PPE

  • 5.16 A register of authorized employees to operate plant / equipment is available

  • 5.17 Keys are to remain in Plant and Equipment when not in use on site

  • 5.18 Stacked items are safe - not overhanging or leaning

  • 5.19 Are pallets in good condition?

6 Electrical

  • 6.1 Condition of leads, plugs etc

  • 6.2 ELCB / RCD used for portable tools

  • 6.3 All equipment tagged correctly

  • 6.4 Leads off ground not near water

  • 6.5 Isolations appropriate & completed

  • 6.6 Earth leads on welders good condition

7 Vehicles and Mobile Equipment

  • 7.1 All vehicles reverse parking

  • 7.2 Road rules are being followed

  • 7.3 Vehicles meet Minepower requirements

  • 7.4 Weekly pre-start inspection completed and logged on all light vehicles

  • 7.5 Daily Pre-start inspection completed and logged on all machinery

  • 7.6 Are they completed by employees

  • 7.7 Are Corrective Actions of defects completed in a timely manner

  • 7.8 Flashing lights & headlights working and being used

  • 7.9 Maintained, clean and sanitary

  • 7.10 Spotter used as required

  • 7.11 Clean / No loose debris

  • 7.12 Radio procedures being followed

8 Traffic Management

  • 8.1 Full segregation of Light Vehicle & Surface Mining Equipment is in place

  • 8.2 Park up areas are correct

  • 8.3 Traffic management plans are in place

  • 8.4 Management plans publicised

  • 8.5 Speed limits are marked correctly

9 Roads and Surfaces

  • 9.1 Windrows correct height

  • 9.2 Surfaces firm and safe

  • 9.3 Roads adequate width

  • 9.4 Delineators in place

10 Excavations and Mining

  • 10.1 Battered back

  • 10.2 Barricaded correctly

  • 10.3 Easy entry and exit to Digger

  • 10.4 Loading of Trucks sequenced

  • 10.5 Correct method of digging is being used

  • 10.6 Dumpy park up defined

  • 10.7 All signals appropriate

11 Job Start

  • 11.1 Job Hazard Analysis (JHA) appropriate & completed

  • 11.2 JHA on the job and understood

  • 11.3 Field Level Risk Assessments (FLRA) have been undertaken

  • 11.4 Permits appropriate & completed

  • 11.5 Isolations appropriate & completed

  • 11.6 Work area demarked and sign posted

  • 11.7 Material Safety Data Sheets (MSDS) for chemicals at the workplace

  • 11.8 Access/egress to work area

12 Occupational Health

  • 12.1 Dust levels low and controlled

  • 12.2 Noise levels acceptable

  • 12.3 Fibrous Material is being controlled

  • 12.4 Vibration is being controlled

13 Hot Work

  • 13.1 Permit in place

  • 13.2 Flashback arresters on cylinders and hand pieces

  • 13.3 All equip (hoses, etc) in good condition

  • 13.4 Fire extinguishers available for all Hot Work

  • 13.5 Earth clamps in correct location

14 Working at Heights

  • 14.1 WAH is being eliminated

  • 14.2 Fall arrest equipment used

  • 14.3 Permit to work at Height in place

  • 14.4 Spotters in place as required

  • 14.5 ECO barricading in place

  • 14.6 Drop zone barricading in place

  • 14.7 Dropped objects prevention is in place

15 Craneage Operations

  • 15.1 Crane log books and documentation in place in the crane

  • 15.2 Cranes set up correctly

  • 15.3 Crane operator competent

  • 15.4 Crane lift risk assessment form in place

  • 15.5 Crane suitable for the task

16 Confined Space

  • 16.1 Confined space permit in place

  • 16.2 Sentry space permit in place

  • 16.3 Procedure being followed

  • 16.4 Space safe

17 Hydrocarbon Storage

  • 17.1 All hydrocarbon materials inside bunds

  • 17.2 Oil spill equipment available, status

  • 17.3 No evidence of stains / spillage

  • 17.4 Bunds fully effective

  • 17.5 Fuel-containing equipment and plant in trays or provided with other bunding

18 Flora and Fauna

  • 18.1 All clearing approved

  • 18.2 VDAs in place for all activities

  • 18.3 Rehabilitation carried out correctly

  • 18.4 Priority flora is identified and fenced

  • 18.5 Topsoil stockpiled and signposted

  • 18.6 No evidence of unauthorized disturbance

  • 18.7 Easy exit for fauna from trenches & pits

  • 18.8 Bore caps in place & conduit ends taped

  • 18.9 All weed free certificates in place

  • 18.10 No weeds growing in project areas

19 Erosion

  • 19.1 No erosion from stockpiles

  • 19.2 No erosion of gullies and streams

20 Chemicals

  • 20.1 Are only approved chemicals being used as per the Approved Chemical Register

  • 20.2 Chemicals stored on site are not expired or obsolete

  • 20.3 Chemicals are not decanted (substances must be in original containers with original labels)

  • 20.4 Are all the chemicals clearly labelled

  • 20.5 Material Safety Data Sheets present at location where Chemicals are kept and easily accessible

  • 20.6 Containers in which chemicals are stored are in good condition and are not leaking

  • 20.7 Nominated area in which chemicals are stored is locked allowing only restricted access and bundled

  • 20.8 Gas bottles secured/ protected from damage or falling over (e.g strapped or chained to secured fixture)

  • 20.9 Is there adequate ventilation where chemicals are stored?

  • 20.10 Spill kits available and fully stocked

  • 20.11 Are emergency showers or eye wash stations available & easily assessable?

21 Explosive Signage and Emergency Equipment

  • 21.1 Prominent "EXPLOSIVE" signs displayed on magazine

  • 21.2 Licence number prominently displayed

  • 21.3 Magazine rules are posted inside the magazine

  • 21.4 "NO SMOKING" signs prominently displayed

  • 21.5 Fire extinguishers are posed at the magazine access

  • 21.6 Manufactures name and date of manufacture displayed on relocatable magazines

22 Explosive House Keeping

  • 22.1 A broom and door mat is available in the magazine to clean up

  • 22.2 No split material is left in the magazine

  • 22.3 The magazine floor is clean and dry

  • 22.4 Explosives are safely stacked to a height no greater than 2 metres

  • 22.5 Air gaps are maintained between explosives and the magazine walls

  • 22.6 No additional unauthorized materials are stored in the magazine

  • 22.7 No explosives are stored loose in the magazine

  • 22.8 Incompatible explosive products are not stored adjacent to each other

  • 22.9 Cladding, vent shrouds and vent gauges are in good condition

  • 22.10 Moulding around the magazine is in good condition where it is a licence requirement

Review

  • Remarks

  • Person completing from

  • Witness/Participant

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.