Information

  • Date of Maintenance:

  • Name of Maintainer:

  • Genset Number:

  • Site:

  • Engine Hours:

  • Work Order No:

PART A - ALTERNATOR / ENGINE WITH ENGINE STOPPED

  • 1. Visually inspect alternator windings

  • Comment

  • 2. Check engine wiring loom for damage

  • Comment

  • 3. Check alternator terminals for loose connections

  • Comment

  • 4. Inspect A.V.R and connections

  • Comment

  • 5. Check and tighten all engine terminal box connections

  • Comment

  • 6. Check cable reeler motor mounts

  • Comment

  • 7. Check oil level OK

  • Comment

  • 8. Check 2 x safety signs

  • Comment

  • 9. Check spare engine oil

  • Comment

  • 10. Check battery holder, posts and clamps, check for corrosion and tightness

  • Comment

  • 11. Check starter motor, solenoid, Redarc, battery isolator connections, operation and inspect for damage and corrosion

  • Comment

  • 12. Check bund sump levels and the area drain is closed

  • Comment

  • 13. Inspect engine mounts for damage

  • Comment

  • 14. Check radiator V belts for damage / tension

  • Comment

  • 15. Check radiator for leaks / damage

  • Comment

  • 16. Check coolant level

  • Comment

  • 17. Check for spare coolant

  • Comment

  • 18. Check fire extinguisher. Secured, pressure OK and within 6 months of last test

  • Last Test Date:

  • Comment

  • 19. Run generator and check for leaks

  • Comment

PART B - CONTROL PANEL

  • 20. Inspect controls integrity

  • Comment

  • 21. Inspect all wiring for loose terminations and connections

  • Comment

  • 22. Check meters

  • Comment

  • 23. Carry out lamp test, replace with L.E.D only

  • Comment

  • 24. Carry out 6 monthly RCD Test and record results on panel sticker

  • Comment

  • 25. Check main Generator C/B. If safe test Close / Open operation

  • Comment

  • 26. Check sync buzzer for operation

  • Comment

  • 27. Check CAN bus terminations and caps

  • Comment

  • 28. Check switches

  • Comment

  • 29. Check MEN connection panel

  • Comment

  • 30. Test output voltages

  • A phase to Neutral (V)

  • B phase to Neutral (V)

  • C phase to Neutral (V)

  • A phase to B phase (V)

  • A phase to C phase (V)

  • C phase to B phase (V)

  • Comment

  • 31. Check batteries charge / float voltages with engine running

  • Record Voltage:

  • Comment

  • 32. Check batteries charge / float voltages with engine off (solar power)

  • Result (V)

  • Comment

  • 33. Inspect Powerlock panel source or lug connectors

  • Comment

  • 34. Inspect labelling and replace any discrepancies or missing labels

  • Comment

  • 35. Clean inside of panels (vacuum and fine brush)

  • Comment

  • 36. Clean outside and top of panels

  • Comment

  • 37. Check all labels and signage for correct and good condition

  • Comment

PART C - CANOPY

  • 38. Check operation of internal LTS

  • Comment

  • 39. Check operation of external LTS

  • Comment

  • 40. Check canopy door locks

  • Comment

  • 41. Check solar panel condition and mounting on canopy roof

  • Comment

  • 42. Check air attenuator mounting bolts are secure

  • Comment

PART D - CABLE CABINET

  • 43. Check Powerlock connections or lug connections on cable for excessive wear and damage

  • Comment

  • 44. Check cable for damage. Repair as required

  • Comment

  • 45. Check 1 x straps

  • Comment

  • 46. Check cable socks. Replace as required

  • Comment

  • 47. Check condition of sync lead and clamp

  • Comment

PART E - EQUIPMENT BOX LEFT SIDE

  • 48. Check 1 x set buss bar clamps (4 heads)

  • Comment

  • 49. Check 1 x set cable, Powerlock to lug for 300kVA

  • Comment

  • 50. Check 1 x Earth Clamp

  • Comment

PART F - EQUIPMENT BOX RIGHT SIDE

  • 51. Check 2 x sets of cable, Powerlock to lug for 500kVA

  • Comment

  • 52. Check 8 x overhead sticks for 500kVA

  • Comment

  • 53. Check 4 x overhead sticks for 300kVA

  • Comment

PART G - GENERAL CHECKS

  • 54. Earthing and connection fittings - continuity between Earth bar and chassis

  • 55. Earthing and connection fittings - continuity between earth & neutral Powerlocks / cable termination points

  • 56. Room and warning system light

  • Comment

  • 57. Lubricate door locks / hinges

  • Comment

  • 58. Fluid bund - Area empty and drain closed

  • Comment

  • 59. Clean generator as required

  • Comment

  • 60. Operation manual - Legible and stored with the generator

  • Comment

  • 61. Log Book - Stored with generator and filled in

  • Comment

  • 62. Fuel card - Caltex and BP cards are present and in date

  • Comment

PART H - PROTECTION AND OPERATIONAL CHECKS

  • Check coolant level protection switch is operational

  • Comment

  • Test Emergency Stop button

  • Comment

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.