Title Page

  • Site

  • Project Manager for start up will be:

  • This site is due to start on:

  • All staff to visit site and sign this page before the start date

  • Site visits:
  • I have visited site

Pre-Start meeting questions

  • These answers MUST be obtained by staff attending the pre-start meeting. Any outstanding information must be followed up by the Project Manager.

  • Who is leading the pre-start meeting on behalf of CRS?

  • The schedule/programme for the initial phase of works has been agreed with CRS?

  • When will a programme be determined?

  • What is the agreed start date?

  • Is there any information that may affect the site setup, from the Pre-Construction information or other?

  • What information do we have that may affect site-setup?

  • Who is responsible for the Construction Phase Plan (CPP)?

  • Who is supplying the CPP?

  • This should be sent to mark.booth@crsplant.co.uk

  • Has the F10 been created and supplied?

  • When will CRS have the F10?

  • This should be sent to mark.booth@crsplant.co.uk

  • Does Daniel Lenton (CRS) have all information regarding Water run-off, TPO, other environmental, overhead services?

  • Date agreed for this information

  • How do we get water into site?

  • How do we get electricity into site?

  • Has the client provided start/finish times and site restrictions to Mark Gladwin (CRS)

  • When will this be agreed?

  • Start/Finish times (if known):

  • Other restrictions (if known):

  • Agree who is providing the following:

  • Skip/Waste Management

  • Agreed date of skip arrival:

  • Vac-Ex

  • Road Sweeper

  • Jet Washer / Gateman

  • Agreed start date of Jet Washer

  • Dust suppression

  • Welfare facilities

  • What is being supplied?

  • Security

  • Name and Contact details for security

  • Start date

  • Have drawings been requested for the attention of Mark Gladwin (CRS)

  • Date sent / due?

  • Is the perimeter already secured by the client?

  • Who is responsible for securing the perimeter?

  • When will the site be secured?

  • Who is supplying the fencing?

  • Is there any fencing currently on site?

  • How many panels?

Mark Booth - Health & Safety and other

  • This section should be completed by the Health & Safety Manager

  • Have the RAMS been written, printed for site and submitted to the client?

  • Has the F10 been received?

  • Is fencing required?

  • Heras panels (inc feet and clips)

  • Heras panels (panel only)

  • Ped Barriers

  • Bunting (metres, inc pins)

  • I have updated the QS regarding any required fence panels?

  • I have updated the Plant Manager regarding any required fence panels?

  • Areas identified for the following:

  • Welfare

  • Parking

  • Large Vehicle Turning area

  • Initial site supervisor or site manager has a Gold Card/SSSTS?

  • What is required

  • Who is it?

  • First Aider designated?

  • Who is it?

  • Action required

  • Is internet required?

  • Why?

  • Is the router new or redistributed?

  • From where?

  • When will it be ready for new site installation?

  • Ordered?

  • Is the router installed?

  • Date for installation

  • Plant check QR code available on-site?

  • Is a laptop and/or tablet required for site?

  • Has this been allocated?

  • Which?

  • Is a new one required?

  • Which?

  • Has this been ordered?

  • Laptop/Tablet on site?

  • Why?

  • H&S Office display ready for installation? (H&S Statement of Intent, Insurance, H&S Poster, F10, SMAS certs and other docs)

  • Date for install

  • Office display Installed?

  • A&E Location identified and displayed

  • Where

  • Policies and induction documents are printed, ready for site?

  • Policies and induction paperwork are on site?

  • Printed office registers ready to go (HAVS, PUWER, LOLER etc)?

  • Office registers are on site

  • Have the required site safety signs been displayed (PPE, Site entrance, Car Park, Pedestrians etc)?

  • Traffic management agreed with Contracts Manager and site manager?

  • Any additional signage required?

  • What is required?

  • Has the additional signage been ordered?

  • Additional signage is on site?

  • PPE checked and is available on site?

  • Water suppression provided and suitable for site/connection type?

  • Does this site require an air-powered mask?

  • Air-Powered Mask on site?

  • Smoking area designated?

  • Fire Assembly point designated?

  • Any fire extinguishers required have been ordered with the CRS Buyer?

  • Fire extinguishers on site?

  • First Aid point displayed and stocked?

  • One Drive H&S File ready for this site?

  • Action required?

Ben Foster - Materials and Buying

  • I have confirmed a delivery route to give to suppliers, considering restricted hours, school traffic etc

  • Note any relevant information

  • Are Concrete rings required?

  • How many?

  • Ordered?

  • Supplier

  • Arrival date and route agreed with supplier

  • Date and delivery area checked with site foreman?

  • Is concrete required?

  • How much?

  • Ordered?

  • Supplier

  • Arrival date and route agreed with supplier

  • Date and delivery area checked with site foreman?

  • Is tarmac required?

  • How much?

  • Ordered?

  • Supplier

  • Arrival date and route agreed with supplier

  • Date and delivery area checked with site foreman?

  • Is hardcore required?

  • How much?

  • Ordered?

  • Supplier

  • Arrival date and route agreed with supplier

  • Date and delivery area checked with site foreman?

  • Other Materials
  • Other materials?

  • How much?

  • Ordered?

  • Supplier

  • Arrival date and route agreed with supplier

  • Date and delivery area checked with site foreman?

  • Plant Manager is aware of the plant and lifting equipment required

  • Who is supplying fuel?

  • Ordered?

  • Delivery date?

  • Checked that fuel storage facilities will be on site

  • Drips trays and absorbent pads ordered/in stock

  • Drips trays and absorbent pads on- site?

  • Spill Kit ordered/in stock

  • Spill kit on site?

  • Oils, coolants and fluids ordered/in stock?

  • Oils, coolants and fluids on site?

  • Grease ordered/in stock?

  • Grease is on site?

  • Adequate number of grease guns and funnels ordered/in stock?

  • Grease guns and funnels on site?

  • Desks and chairs ordered/in stock

  • Desks and chairs on site?

  • Filing cabinet/drawers ordered/in stock?

  • Filing cabinets/drawers on site?

  • Key safe ordered/in stock

  • Stationary is ordered, or in stock (pens, markers, stapler, hole punch, sellotape).

  • Stationary is on site

  • Printer and paper, laminator and laminate pouches ordered for site

  • Printing and laminating is available on site

  • Blades ordered/available for Stihl Saws?

  • Saw blades are on site

  • Office, canteen and/or toilet waste bins ordered

  • Bins on site

  • Kettle, microwave, mugs ordered/in stock

  • Kitchen facilities on site

  • Water cooler and water ordered/in stock

  • Water on site

  • Site Safety sign pack ordered/in stock (Site PPE, Car Park, Site Entrance, Speed Limit etc)

  • Pedestrian route signs ordered/in stock

  • Toilet roll, blue roll, paper towels, toilet brush and basic cleaning products ordered/in stock

  • Toilet rolls and cleaning products on site as required

  • Extension leads ordered/in stock?

  • Extension leads on site

  • Are fire extinguishers required (as requested by H&S)

  • Have fire extinguishers been ordered?

  • Chapter 8 barriers or signage required for works in road?

  • How many?

  • Full amount in stock already

  • Ordered

  • Arrived on site

  • Action required?

Richard Howell - Plant, Buildings and storage facilities

  • All plant has been allocated to site? (Large and small plant, including jet wash)

  • What plant is going to site?

  • Date due?

  • All plant has arrived

  • Lifting equipment has been allocated to site?

  • What lifting equipment is going to site?

  • Date due?

  • All lifting equipment has arrived and is suitable for work required and unloading materials due?

  • A suitable storage area for large and small plant items have been identified?

  • Plant testing and LOLER certificates checked and on the system

  • Is there a suitable connection or supply of water on site for the jet wash?

  • Lasers available for site?

  • Lasers and associated equipment on site, or with engineer/operative

  • A suitable site office has been identified

  • Due date?

  • Arrived at site?

  • Suitable toilet for number of operatives on site identified

  • Due date?

  • Arrived at site?

  • Canteen with hot/cold running water and adequate seating identified

  • Due date?

  • Arrived at site?

  • Changing room / Heating / Drying Room required?

  • Changing room / Heating / Drying room ordered as required?

  • Due date?

  • Arrived at site?

  • Welfare service connections required

  • Arranged?

  • Date

  • COSHH storage arranged?

  • COSHH storage on site?

  • Diesel bowser arranged

  • Diesel bowser on site

  • Are we supplying a skip?

  • Ordered

  • Date due

  • Are we supplying Road Sweeper?

  • Ordered

  • Date due

  • Is Vac-Ex required yet?

  • Ordered

  • Date due

  • Are we supplying any ground dust suppression?

  • Ordered

  • Date due

  • Locks and chains required for site entrance gate and cabins

  • Locks and chains ordered/in stock

  • Locks and chains on site

  • Cleaner Required

  • Cleaner arranged

  • Day cleaner due

  • The H&S Manager has requested the following barriers

  • Heras panels (inc feet and clips)

  • Full amount in stock already

  • Ordered

  • Arrived on site

  • Heras panels (panel only)

  • Full amount already in stock

  • Ordered

  • Arrived on site

  • Ped Barriers

  • Full amount already in stock

  • Ordered

  • Arrived on site

  • Bunting (metres, inc pins)

  • Full amount already in stock

  • Ordered

  • Arrived on site

  • Action required?

Daniel Lenton - Technical and other

  • Drawings in hand for initial phase of works?

  • Have these been requested?

  • Due date

  • These have been shared with the relevant people

  • Any relevant geological or topographical information, ground type etc

  • This has been shared with the relevant people

  • Is there any CBR testing info received from remediators?

  • Has this been requested?

  • Due date

  • CBR Information

  • Additional information of relevance from the client or previous contractors

  • This has been shared with the relevant people

  • An engineer has been allocated to this site

  • Who is the engineer at this site?

  • Date given for survey start dates?

  • When?

  • Other works required
  • Any other works required?

  • What works are required?

  • Has this been arranged?

  • Date of other works

  • The initial required materials have been decided and finalised

  • This information has been given to the CRS buyer

  • Partial information has been given to the CRS Buyer

  • Which material details are not yet finalised?

  • Do you have all information regarding Water run-off, TPO, other environmental, overhead services?

  • Date agreed for this information

  • Provide any information

  • Has this been shared with the relevant people?

  • One Drive site file has been created and shared

  • Site manager requires a telephone/sim card

  • Telephone ordered

  • Sim card ordered

  • Applications required
  • Please select the application required?

  • Application type required

  • Has this application been submitted

  • Has this application been approved

Relevant reference numbers obtained from client:

  • NHBC Inspector Number:

  • Highways Inspector Number:

  • Section 104 number:

  • Action required?

Mark Gladwin - Estimating, Initial client agreements and information

  • Start finish times have been confirmed

  • Start

  • Finish

  • Are there any other site restrictions?

  • Please provide details

  • Are CRS required to provide a jet washer / gateman?

  • Have you told the plant manager and contracts manager?

  • Drawings requested from client

  • Drawings received from client

  • Date due

  • Tender drawings/any superseding drawings have been passed to Technical Manager

  • Superseding drawings
  • Received on

  • Passed to Technical manager

  • Action required?

QS - Michael Roberts, Greg Kendall, Alfie Wright

  • Are we required to provide security

  • Has security been arranged?

  • Who is the security company

  • Contact details

  • Install date

  • Who will provide access

  • Liaise with Plant Manager and H&S Manager for details of barriers being ordered

  • Heras panels (inc feet and clips)

  • Cost confirmed with plant manager

  • Charged to

  • Heras panels (panel only)

  • Cost confirmed with plant manager

  • Charged to

  • Ped Barriers

  • Cost confirmed with plant manager

  • Charged to

  • Bunting (metres, inc pins)

  • Cost confirmed with plant manager

  • Charged to

  • Are any additional footpaths required, or any areas for stoning up?

  • This will be paid for by

  • This has been confirmed with them

  • Additional information

  • Any Construction Issue Drawings, Specification, Programme, Bill of Quantities (Supplied by Quantity Surveyor)

  • Has this been shared with the relevant people?

  • Action required?

Darren Houghton - Contracts Manager

  • Who is the initial supervisor at this site?

  • Start date

  • Aware

  • Is this the permanent supervisor

  • Who is the permanent supervisor at this site?

  • Start date

  • Aware

  • Operatives have been allocated to site for the start date and have been made aware

  • I have checked with H&S that they have the required competencies, cards and/or qualifications for their role

  • Will we be carrying out works in road?

  • I have checked with H&S that streetworkers have the required competencies, cards and/or qualifications for their role

  • I have told the CRS Buyer, so he can order relevant Chapter 8 barriers and source signage

  • I have confirmed with the Technical Manager that the required permits will be in place

  • Suitable area identified on site for spoil

  • Where?

  • Suitable area identified on site for materials

  • Where?

  • Temporary services arranged

  • Water

  • Electricity

  • Confirm if all required services are connected

  • The estimating manager has confirmed to me that we are required to supply a gateman / jet washer

  • Start date confirmed with an operative to carry out this role

  • Action required?

Project Manager Setup Completion

  • I can confirm that I have reviewed the information and that site operation is ready to commence

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.