Title Page

  • Site conducted

  • Inspection Date

  • Lot Number

  • Works Description

  • Concrete Core Fill Strength

  • Concrete Strength 20 MPa or above with 10mm Aggregate?

  • Concrete Core Fill Slump

  • Slump to be 225mm +/- 15mm

  • Concrete Qty

  • Pump Required

  • Water Added

  • How Much?

  • Correct Setout of Block Base - RPS Survey Pin Corners of Blockwork

  • Correct Blockwork Reinforcement as per Latest IFC Drawings

  • Correct Starter Bar Reinforcement - N16 Starters at 200mm Centres with 400mm Lap Length

  • Correct Vertical Bar Reinforcement - N16 Bar at 200mm Centres

  • Correct Vertical Bar Reinforcement (Perimeter Pier Blocks) - 4-N16 Bars with N10 LIGS at 200mm Centres

  • Correct Vertical Bar Reinforcement (Internal Pier Blocks) - 4-N12 Starter Bars with 400mm Lap Length, N12 Vertical Bar with N12 LIGS at 150mm Centres

  • Correct Horizontal Bar Reinforcement - N12 Bar at 600mm Maximum Centres

  • HOLD POINT - PRE-POUR INSPECTION by STP Consultants

  • Inspector Name & Signature

  • Complete Concrete Pour Record Sheet

  • Take Photos of Concrete Dockets

ITP Sign OFF

  • ITP Sign Off - FERGUS BUILDERS

  • ITP Sign Off - STP CONSULTANTS

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.