Title Page
-
Site conducted
-
Inspection Date
-
Pour Date
-
Lot Number
-
Pour Description
-
Correct Setout of Inline Thrust Block as per Latest IFC Drawings & to Suit Pipework & Pumps Layout
-
Install Formwork. Formwork to be Clean & Free of Organic Matter
-
Prep & Place Correct Reo to Inline Thrust Block - N16 600mm Threaded Rod screwed into N16 Ancon Qwikfoot Anchors. N12 Bar Horizontal & Vertical, Each Face at 150mm Centres tied with N12 U-Bars at 150mm Centres.
-
Order Correct Strength of Concrete - Strength?
-
Concrete Strength N40 or above?
-
Concrete Slump
-
Concrete Qty
-
Pump Required
-
Water Added
-
How much?
-
HOLD POINT - PRE-POUR INSPECTION by STP Consultants
-
Inspector Name & Signature
-
Pour Inline Thrust Block
-
Vibrate all Concrete
-
Strip Formwork & Clean
-
Complete Concrete Pour Record Sheet
-
Take Photos of Concrete Dockets
ITP Sign OFF
-
ITP Sign Off - FERGUS BUILDERS
-
ITP Sign Off - STP CONSULTANTS