Title Page

  • Site conducted

  • Inspection Date

  • Pour Date

  • Lot Number

  • Pour Description

  • Correct Setout of Inline Thrust Block as per Latest IFC Drawings & to Suit Pipework & Pumps Layout

  • Install Formwork. Formwork to be Clean & Free of Organic Matter

  • Prep & Place Correct Reo to Inline Thrust Block - N16 600mm Threaded Rod screwed into N16 Ancon Qwikfoot Anchors. N12 Bar Horizontal & Vertical, Each Face at 150mm Centres tied with N12 U-Bars at 150mm Centres.

  • Order Correct Strength of Concrete - Strength?

  • Concrete Strength N40 or above?

  • Concrete Slump

  • Concrete Qty

  • Pump Required

  • Water Added

  • How much?

  • HOLD POINT - PRE-POUR INSPECTION by STP Consultants

  • Inspector Name & Signature

  • Pour Inline Thrust Block

  • Vibrate all Concrete

  • Strip Formwork & Clean

  • Complete Concrete Pour Record Sheet

  • Take Photos of Concrete Dockets

ITP Sign OFF

  • ITP Sign Off - FERGUS BUILDERS

  • ITP Sign Off - STP CONSULTANTS

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.