Title Page
-
Site conducted
-
Inspection Date
-
Pour Date
-
Lot Number
-
Pour Description
-
Correct Setout of Footings as per Latest IFC Drawings & Surveyor Setout. Profiles to be setup from surveyed grid lines.
-
Excavate Correct Depth of Footings - 400mm Thick with 50mm Blinding Layer. RL 4.1 = Top of Blinding Layer. RL 4.5 Top of Footing
-
Excavate Correct Width of Footings as per Latest IFC Drawings - 750mm wide, 1400mm wide or 1585mm wide
-
Order Correct Concrete Strength for Blinding Layer
-
Concrete Strength N20 or above?
-
Concrete Slump
-
Concrete Qty
-
Pump Required
-
Water Added
-
How much?
-
Pour Concrete Blinding Layer
-
Install Formwork where required. Formwork to be Clean & Free of Organic Matter
-
Prep & Place Correct Reo as per Latest IFC Drawings - N16 Bar Top & Bottom at 150mm Centres with N12 Ties at 200mm Centres. 80mm bottom cover & 45mm cover to top and sides.
-
Prep & Place Correct Stair Footings Reo as per Latest IFC Drawings - 8 N12 Bars with N10 Ties at 175mm Centres. 80mm bottom cover & 45mm cover to top and sides.
-
Prep & Place Starter Bars as per Latest IFC Drawings - N12 Starter Bars at 200mm Centres with 400mm Lap Length
-
Order Correct Concrete Strength for Footings
-
Concrete Strength N40 or above?
-
Concrete Slump
-
Concrete Qty
-
Pump Required
-
Water Added
-
How much?
-
HOLD POINT - PRE-POUR INSPECTION by STP Consultants
-
Inspector Name & Signature
-
Pour Concrete Footings
-
Vibrate all Concrete
-
Strip Formwork & Clean
-
Complete Concrete Pour Record Sheet
-
Take Photos of Concrete Dockets
ITP Sign OFF
-
ITP Sign Off - FERGUS BUILDERS
-
ITP Sign Off - STP CONSULTANTS